Industrial & Manufacturing › Energy, Utilities & Sustainability › Renewable Energy & Storage

Wind Energy Development

Long-cycle programs where regulation, capital, and grid reliability define the pace.

Example organizations in this space: Vestas Siemens Gamesa GE Vernova Ørsted

This interactive experience is the shipped product itself — the same application code customers run in production, mounted read-only in your browser over a real sample journey. Not a video, not a mockup: because the demo and the product are one codebase, it can never drift from the real thing.

Inside this journey
  1. Pre-Sales

    Qualify and diagnose technical, commercial, and permitting risks before committing resources.

    1. Qualification

      Confirm budget range, decision-makers, timeline, and high-level risk tolerance before investing in detailed technical discovery.

      Qualification Questions

      Project and Site Fit — a quick snapshot so we can judge technical and scope alignment before a full discovery

      • Roughly what is the intended project size? Options: <50 MW (below typical minimum), 50–199 MW, 200–499 MW, 500–999 MW, 1,000 MW or more (may need bespoke support)
      • What best describes your current site readiness (resource studies, land access, permitting constraints)? Options: Independent wind resource study complete, Preliminary resource data only, Site not yet assessed, Site assessed and significant constraints identified
      • What is the project's interconnection status? Options: No interconnection application started, In queue; position known, In queue; position pending, Interconnection agreement secured

      Commercial and Technical Fit — headline choices that affect scope, commercial model, and turbine selection

      • Which commercial structure are you primarily evaluating for this project? Options: Long-term PPA, Build-transfer or turnkey sale, Turbine supply only, Joint venture or equity partnership, Undecided / evaluating options
      • Do you have turbine platform preferences or site wind regime requirements we should know about?

      Budget, Decision Authority, and Timing — concise signals that determine whether a full discovery is the right next step

      • If available, please summarize any allocated budget or target PPA/LCOE range for this project (optional)
      • Who is the primary decision-maker for moving to a full discovery and who else must sign off?
      • What is your target decision or commercial close timeframe and what is primarily driving that timing? Options: Under 3 months, 3–6 months, 6–12 months, 12+ months, No set timeline yet
    2. Resource & Site Discovery

      Capture wind resource studies, site constraints, permitting status, interconnection position, and stakeholder map needed to size and price the project.

      Discovery Questions

      Getting Oriented Together

      • Tell me the simple story of this opportunity in one paragraph, including site, target capacity, and your main target outcome.
      • How many megawatts are you targeting for this site? Options: <50 MW, 50–100 MW, 100–250 MW, 250–500 MW, 500+ MW
      • Who on your team must sign off on a go or no-go decision? Options: Development / Project Lead, Procurement, Finance, Legal / Contracts, Executive / Board
      • When do you need first commercial operation or financial close? Options: Within 3 months, 3–6 months, 6–12 months, 12+ months, Undecided
      • Describe the commercial structure you are leaning toward, for example PPA, build-transfer, joint venture, or turbine supply plus services. Options: PPA, Build-transfer, Joint venture, Turbine supply with full services, Undecided
      • Walk me through any hard dates or regulatory obligations that drive your timeline.
      • Is there a fixed regulatory or board deadline that would force you to cancel the project if not met? Options: Yes, a specific date is set, Yes, within a defined window, No fixed deadline, Unsure

      Where the Wind Really Is

      • If your modeled annual energy production were overstated by 10 percent, how would that change your team's willingness to proceed?
      • Which wind dataset sources do you currently rely on, pick all that apply Options: Long-term measured (met mast / LiDAR, 5+ years), Short-term campaign (<2 years), Reanalysis / mesoscale model, Independent vendor energy assessment, No formal datasets
      • How many years of on-site measurement (met mast or LiDAR) do you have? Options: None, <1 year, 1–2 years, 3–5 years, 5+ years
      • Describe how you perform long-term adjustment to measured wind data and whether a third party has validated that approach.
      • What single resource finding, such as low mean wind, high turbulence, or a problematic shear profile, would make you stop sizing this site?
      • Are the primary datasets you reference shareable, and who holds permission to distribute them? Options: Owned by your team and shareable, Held by a consultant, permission needed, Held by a third party and restricted, No formal owner identified

      Site Constraints That Scale or Stop Projects

      • Which single site constraint would stop this project in its tracks if unresolved?
      • Tell me about any soil, groundwater, or foundation constraints already identified on site.
      • Select the access constraints that apply to your site, pick all that apply Options: Limited road access, Protected habitat nearby, Seasonal access restrictions, Crane placement constraints, No significant access issues identified
      • When was the last geotechnical or topographic survey performed for the primary turbine areas? Options: Not done, <6 months, 6–12 months, 1–3 years, 3+ years
      • Provide the number of laydown and storage areas available and indicate whether they are secured.
      • If the foundation solution required piles instead of gravity bases, would that budget change be a deal breaker? Options: Yes, materially a deal breaker, Somewhat, would trigger redesign, No, manageable within budget, Unsure

      Who Else Is in the Room — The Options You Are Weighing

      • List the alternatives you are actively considering, and indicate which option would let your team avoid changing vendors or partners.
      • Select from the following which options you have already evaluated Options: Incumbent developer, In-house development by your team, Other turbine OEMs, Different technology (solar, storage), Postpone project, No alternatives evaluated yet
      • What conditions would have to remain true for you to keep working with the incumbent or pursue an in-house approach instead of switching?
      • Has anyone on your team proposed solving this internally without an outside partner? Options: Yes, widely proposed, Yes, suggested by a few stakeholders, No, not proposed, Unsure
      • Imagine the incumbent offered improved commercial or schedule terms tomorrow, what single change would get you to pause conversations with new partners?
      • Rank the evaluation criteria that will most influence your choice Options: Price / PPA cost, Execution track record, Schedule certainty, Availability guarantees and service, Risk allocation, Local community acceptance

      Interconnection and Queue Reality

      • Assume the interconnection window slips by a year, what would that do to your financing, offtake, or project viability?
      • Identify the interconnection queue stage your project is currently in Options: Not submitted, Feasibility study, System impact study, Facilities study, Ready to construct / agreement in place, Unknown
      • Who owns the interconnection studies and can those reports be shared with potential suppliers? Options: Your team, Grid operator, Consultant, Unknown / not available
      • Provide the constrained capacity, in megawatts, of the nearest point of interconnection if known.
      • Are commercial constraints like capacity allocation or expected curtailment quantified for the site? Options: Yes, quantified (MWh or %), Qualitative estimate only, Not assessed
      • Name the interconnection outcome that would force you to stop or postpone the project immediately.

      Permitting, Land, and the People Who Matter

      • Point to the permitting or land issue that has the ability to impose the longest delay on this project.
      • List the permits that are still outstanding, pick all that apply Options: Environmental assessment or EIA, Zoning / conditional use, Construction permits, Bird and bat impact studies, Cultural resources surveys, None required / complete
      • Indicate which party holds the land rights and whether leases or easements are signed Options: Owner signed leases in place, Option agreements / rights to negotiate, Verbal agreements only, No agreements secured, Undecided
      • Summarize any organized community opposition or local stakeholders likely to object.
      • Assuming a single opposition campaign emerged, what mitigation or commitments would prevent it from blocking permits? Options: Mitigation plan exists, Community benefits package ready, Legal defenses prepared, No clear mitigation available, Unsure
      • Is there a legal or regulatory exclusion that could prohibit turbines in key parts of the site? Options: Yes, No, Unknown

      Operational Readiness and Practical Constraints

      • Imagine we could deliver a complete turbine package next month, does your team have the land access, grid permissions, and O&M budget to accept delivery? Options: Yes, fully ready, Partially ready, some gaps, No, major gaps, Unsure
      • Identify the internal teams expected to support construction and name your single point of contact Options: Development / Project, Construction / EPC, Operations / Asset Management, Procurement, External EPC / Owner's engineer
      • Confirm whether your SCADA and operations data infrastructure can accept OEM interfaces and note any missing APIs. Options: Yes, native APIs available, Yes, adapters required, No, needs development, Unknown
      • Rate the maturity of your asset management process for warranty and service claims Options: Established with SLAs and workflows, Informal process, No process in place, Outsourced to third party
      • Name the team or role that will own availability and performance monitoring after commercial operation.
      • Do you have financing covenants or procurement constraints that require specific delivery windows or vendor qualifications? Options: Yes, strict covenants, Some vendor requirements, No specific covenants, Unsure
      • Specify the single operational constraint that would force you to delay or cancel procurement.

      Decision Drivers and Next Steps

      • Assuming a pilot proves the modeled output, what would stop you from signing the full agreement that week?
      • Indicate the commercial metrics that will determine go or no-go, pick all that apply Options: PPA price, IRR / NPV, Availability guarantee, Modeled LCOE, Payback period, Other
      • Estimate when you expect to reach a commercial decision Options: Within 2 weeks, Within 1 month, 1–3 months, 3–6 months, Longer / Unsure
      • Pinpoint the board or executive roles that need to be convinced and the evidence that will move them.
      • Specify the onboarding documents or datasets you would need from the seller to accelerate your review Options: Full resource dataset, Geotechnical report, Interconnection studies, Detailed turbine specifications, Commercial term sheet
      • Would a site visit or joint technical review shorten your timeline? Options: Yes, it would shorten the timeline, Maybe, it could help, No, not necessary
      • Confirm whether you are prepared to share the primary datasets and a point of contact to move to detailed pricing Options: Yes, ready to share, Yes, pending internal approvals, Not yet, No
  2. Solution Experience

    Walk through how turbine choice, site layout, commercial structure, and O&M programs deliver the buyer's outcomes in realistic operating scenarios.

    Solution Experience

    • Solution Experience Session
    • Run a site- and interconnection-specific 20-year energy and availability scenario set, including baseline and two downside wind years, and deliver the results before the follow-up decision meeting.
    • You confirm that the modeled AEP and availability in the presented scenarios meet your minimum thresholds for PPA pricing and financing.
    • Confirm the current state and its cost
    • Walk through generation and availability scenarios
    • You confirm that the proposed commercial structure produces acceptable financing metrics under the shown downside cases.
    • Provide a draft commercial structure module showing PPA pricing sensitivity, payment triggers, and risk allocation for buyer review.
    • You confirm that the O&M program and responsibility split address the operational risks you raised.
    • Validate commercial structure outcomes
    • Provide the most recent wind resource study, micrositing assumptions, and current interconnection queue status.
    • Provide finance and procurement minimums for modeled AEP, availability, and allowed price range needed to proceed to board or credit committee review.
    • You agree on the remaining evidence and deliverables needed to reach mutual commit.
    • Demonstrate O&M program impact on availability and lifecycle cost
    • Validation checkpoint
    • Solution Experience Session
    • Solution Experience Deck
    • Solution Brief
    • meeting
    • slides
    • document
  3. Solution Scope

    Define project boundaries, turbine platforms, BOP scope, responsibilities, schedule assumptions, and measurable acceptance criteria.

    1. Solution Scope

      Define project boundaries, turbine platforms, BOP scope, responsibilities, schedule assumptions, and measurable acceptance criteria.

      Scope Configuration

      • Manufacture and Deliver Turbine Units (3–15+ MW)
      • Transport and Install Nacelles, Towers, and Blades
      • Install Met Mast and Long‑term Resource Monitoring Equipment
      • Construct Foundations, Access Roads, and Crane Pads
      • Install Electrical Collector System and Onsite Substation
      • Manage Grid Interconnection Construction and Queue Position
      • Commission Plant and Perform Performance Acceptance Testing
      • Provide Full‑Service Operations and Maintenance Agreement
      • Deploy SCADA Monitoring Platform and Predictive Analytics
      • Blade Inspection, Repair, and Retrofit Services
      • Gearbox and Generator Overhaul, Exchange, and Repair
      • Supply Spare Parts and Local Inventory Management
      • Structure Commercial Contract and Financing Package (PPA/JV/BT)
      • Manage Tax‑Credit and Incentive Applications and Monetization
    2. Scope Questions

      Scope Questions

      Manufacture and Deliver Turbine Units (3–15+ MW)

      • Which nameplate power rating range do you require for turbine supply? Options: 3–6 MW, 6–9 MW, 9–12 MW, 12–15+ MW
      • Do you have a preferred rotor diameter or specific swept area requirement for the site wind regime? Options: Yes — specify hub height and rotor diameter, No — recommend for us
      • How many turbine units are in scope for delivery under this package?
      • Provide the factory acceptance test (FAT) expectations you require (for example witness scope, test report deliverables, and torque/power curves).
      • Identify maximum blade length and nacelle gross weights your site logistics permit (meters and tonnes).
      • Estimate target turbine lead time from order to delivery (months). Options: <6 months, 6–12 months, 12–18 months, 18+ months

      Transport and Install Nacelles, Towers, and Blades

      • Do you have a route survey or transport constraints documented (maximum axle load, bridge limits, permitted convoy hours)? Options: Yes — route survey attached, No — need route planning
      • List required permits or escort arrangements your local authority mandates for oversized load movement.
      • Describe the on‑site crane requirements and availability window (crane heights, lifting capacity per lift, number of parallel lifts).
      • Specify any local restrictions on night transport, blade overhang, or road closures that affect installation sequencing.
      • Confirm whether you require us to manage grass‑roots road upgrades or third‑party contractor coordination for oversized deliveries. Options: Yes — include upgrade scope, No — buyer provides upgrades, Need recommendation
      • Indicate the maximum single blade length that can travel without additional permitting (meters).

      Install Met Mast and Long‑term Resource Monitoring Equipment

      • Specify the measurement heights required for site resource validation (for example hub height, hub+10 m).
      • Which instrument types must be included on the mast (anemometer cup/vane, sonic, pitot, wind lidar) and at which heights?
      • Do you require remote telemetry to your SCADA or a platform endpoint; if so, list preferred protocols and telemetry points (for example 10‑minute average wind speed, temperature, humidity).
      • What is your expectation for instrument calibration traceability (for example calibration certificates, calibration lab name, interval months)? Options: Initial calibration certificate only, Initial plus annual calibration, Initial plus biannual calibration
      • What evidence will validate long‑term wind data collection (for example anemometer calibration certificates, data continuity >= 95% over 12 months, timestamped QC reports)?
      • Identify any site security or anti‑tamper requirements for mast equipment (fencing, GPS anti‑tamper, camera). Options: Fencing required, GPS anti‑tamper required, Camera monitoring, No additional security

      Construct Foundations, Access Roads, and Crane Pads

      • Do you have a completed geotechnical report for each turbine location including allowable bearing pressure and groundwater table depth? Options: Yes — attach reports, No — require geotech scope
      • Specify the foundation type preferred or required by local conditions (shallow spread footing, piled foundation, rock anchor, gravity mat). Options: Spread footing, Piled foundation, Rock anchor, Gravity mat, Undetermined — need design
      • Describe access road upgrade requirements including maximum gradient, axle load design, and seasonal restrictions.
      • Indicate required concrete specification and testing protocol for foundations (compressive strength MPa, cube/cylinder testing schedule).
      • Provide any environmental constraints that affect foundation schedule (restricted works windows for nesting season, wet season restrictions).
      • State who will be responsible for spoil removal and topsoil reinstatement after pad and road construction. Options: We handle, You provide contractor, Shared responsibility — define in contract

      Install Electrical Collector System and Onsite Substation

      • Which single‑line diagram (SLD) or one‑line configuration should the collector and substation follow (include transformer ratings and bus arrangement)?
      • Identify conductor sizes and preferred cable types for the collector network (for example XLPE 33 kV, 34.5 kV, 66 kV) and expected route lengths.
      • Do you require station service designs, auxiliary power, and backup generation during commissioning? Options: Yes — specify requirements, No — buyer provides
      • Which protection and control relay settings or standards must be met at handover (for example inverse time overcurrent, distance protection, IEC 60255 compliance)?
      • What acceptance tests and thresholds (for example insulation resistance > X MΩ, transformer turns ratio within Y%, relay pick-up verification) will validate the collector system and onsite substation?
      • Confirm required earthing/grounding resistance target and lightning protection standard for the substation.

      Manage Grid Interconnection Construction and Queue Position

      • What is your point of interconnection (POI) and the transmission owner or utility queue ID associated with this project?
      • List the completed interconnection studies you have (feasibility, system impact study (SIS), facilities study) and attach any outstanding study deliverables. Options: Feasibility only, SIS complete, Facilities study complete, No studies complete
      • Who is responsible for funding required network upgrades and where do you expect cost responsibility to lie (buyer funded, utility funded, shared)? Options: Buyer funds, Utility funds, Shared — propose split
      • By when must interconnection be energized to meet your commercial schedule (month/year)?
      • Describe any queue‑position remedies you expect (deliverability reservations, milestone extensions, rights to transfer queue position).
      • Indicate any required studies or mitigations for system stability or short‑circuit duty the transmission owner flagged.

      Commission Plant and Perform Performance Acceptance Testing

      • Which performance standard will determine acceptance testing (for example IEC 61400‑12‑1 power performance test protocol)? Options: IEC 61400‑12‑1, Other documented protocol — specify, Project‑specific procedure
      • How many turbines should be subject to power performance testing vs. sampling inspection? Options: 100% tested, Sampling per IEC (specify sample size), Custom sampling plan
      • Describe the site environmental and wind condition windows acceptable for performance testing (turbulence intensity limits, wind speed bins, temperature range).
      • Who will witness commissioning and performance acceptance tests and which documentation must they sign (commissioning checklist, power curve report, SCADA logs)?
      • What measurable acceptance criteria will confirm each turbine meets the guaranteed power curve and availability (for example gross electrical output within X% of guaranteed P50, availability >= 97% annualized)?
      • Indicate required post‑acceptance deliverables (as‑installed single‑line diagrams, commissioning certificates, SCADA historian data export).

      Provide Full‑Service Operations and Maintenance Agreement

      • What contract term length do you require for full‑service operations and maintenance (years)? Options: 1–3 years, 4–7 years, 8–15 years, Custom term
      • Which availability or uptime SLA targets do you expect (percent availability annualized) and are there liquidated damages tied to shortfalls?
      • Do you want proactive predictive maintenance using SCADA analytics and vibration trend monitoring included? Options: Yes — include predictive suite, No — condition‑based only, Partial — specify modules
      • Specify the scope of spare part provisioning you expect under the agreement (on‑site spares, exchange pool, consignment inventory).
      • Who will hold statutory maintenance records and safety documentation required for regulator inspections? Options: We maintain and provide, You maintain, Shared — specify deliverables
      • Identify required response time tiers for corrective events (for example 24 hours for critical faults, 72 hours for noncritical).

      Deploy SCADA Monitoring Platform and Predictive Analytics

      • Which SCADA telemetry points are mandatory at handover (for example rotor speed, generator power, nacelle yaw, vibration channels, pitch angle)?
      • Which communication protocol and interface will you accept for SCADA integration (for example IEC 61850, OPC, Modbus TCP)? Options: IEC 61850, OPC UA, Modbus TCP, Custom — specify
      • Describe your expected reporting cadence and dashboard KPIs (for example hourly energy, daily availability, alarm rates).
      • Indicate data retention and export requirements for the SCADA historian (retention years, CSV/SQL export frequency).
      • Do you require role‑based access and single sign‑on integration with your identity provider for SCADA users? Options: Yes — SSO required, No — platform accounts ok, Need recommendation
      • Specify expected predictive analytics deliverables (fault prediction horizon, remaining useful life estimates, monthly anomaly reports).

      Blade Inspection, Repair, and Retrofit Services

      • What inspection interval do you prefer for blades (visual every X months, detailed UAV or rope access every Y years)? Options: Visual quarterly, Visual semiannual, Detailed annual, Custom schedule
      • Which inspection modalities do you require (rope access, drone/UAV photogrammetry, thermographic, borescope)? Options: Rope access, Drone/UAV, Thermographic, Borescope, Other
      • Describe acceptance thresholds for blade condition that would trigger repair or replacement (for example leading edge erosion > X mm, composite delamination area > Y cm^2).
      • Do you require blade retrofit options such as vortex generators or LE (leading edge) protection; if so, which performance objective are you targeting? Options: Leading edge protection, Vortex generators, Aerodynamic retrofit, No retrofit required
      • What is your maximum allowable turnaround time for an urgent blade repair once a work order is raised? Options: <48 hours, 48–120 hours, 120+ hours
      • Indicate whether you require post‑repair performance verification (for example power curve recheck on repaired turbine). Options: Yes, No
  4. Mutual Commit

    Finalize commercial structure, contract modules, performance guarantees, and mutual obligations required to proceed to construction.

    Agreement Modules

    • Commercial Structure Confirmation
    • Power Purchase Agreement (PPA) — Execution Copy
    • Equipment Supply Agreement (Turbine Supply Contract)
    • EPC Contract (Balance-of-Plant Construction Agreement)
    • Operations & Maintenance (O&M) Agreement
    • Performance Guarantees & Liquidated Damages Schedule
    • Security Package (Guarantees, Bonds, Escrow)
    • Pre-Construction Conditions Precedent
    • Interconnection & Permitting Responsibility Addendum
    • Schedule & Payment Milestones (Order Confirmation)
    • Insurance & Indemnity Schedule
    • Mutual Commit Certificate
  5. Construction & Commissioning

    Coordinate construction, grid interconnection, and safety sign-offs required to energize the project.

    1. Pre-Deployment Readiness

      Confirm owners, land access, permitting milestones, interconnection deliverables, and procurement lead times required before construction starts.

      Pre-Deployment Questions

      Environment and site access

      • How many distinct construction sites (plants/parcels) are included in this project? (so we can create per-site readiness tasks)
      • Per site, what is the current land-access status? Select all that apply across your sites (we'll use this to generate per-site actions) Options: Fully secured (leases/easements/executed agreements), Secured with conditions or effective date pending, Access agreements in negotiation, No access arrangements signed, Not applicable (single consolidated site)
      • For any site marked 'Fully secured' or 'Secured with conditions', what is the contractual date when full physical access is guaranteed? (earliest date per site)

      Data and critical deliverables

      • Which of the following critical pre-construction deliverables are completed and assigned to an owner? (select all that apply — this determines what the deployment team can execute immediately) Options: Interconnection agreement/execute-ready LGIA, Transmission/short-circuit study completed, Permits issued with construction conditions, Geotechnical/site investigation report, Final wind resource & micrositing report, None of the above
      • For any deliverable you selected as outstanding, provide the committed delivery date or milestone (earliest expected date) so we can gate construction start accordingly

      People and ownership

      • Who is the single point of contact (name and role) responsible for construction mobilization and site access approvals? (this person will receive schedule and permitting calls-to-action)
      • Who is the named owner responsible for interconnection acceptance, utility coordination, and pre-energization approvals? Options: The buyer (off-taker/owner), The seller (developer/OEM), Third-party contractor retained by buyer, Third-party contractor retained by seller, Not yet assigned
      • Are procurement lead times for long‑lead items (turbine platforms, blades, transformers) committed? Select the best status (we'll request schedules for anything marked committed) Options: Yes — lead times committed for all long‑lead categories, Partially — some categories committed, others pending, No — lead times not confirmed

      Timing and constraints

      • If any procurement lead times are 'Yes' or 'Partially', list each long‑lead category and the earliest confirmed delivery month (so we can align construction mobilization). If none, leave blank.
      • Are there regulatory, environmental, utility, or seasonal blackout windows or critical dates we must avoid? Select all that apply (these constrain allowable construction/energization windows) Options: Local/regulatory moratoriums or milestone gating, Wildlife/bird or bat seasonal restrictions, Utility outage/blackout windows, Road/seasonal access restrictions (e.g., winter closures), No known constraints, Other (will describe)
    2. Configuration Details

      Lock technical parameters the project team will use—turbine specs, commissioning thresholds, SCADA interfaces, and O&M handover criteria.

      Configuration Details

      ENVIRONMENTS & ENDPOINTS

      • Enter the project environment name used in provisioning (format: short, lowercase, no spaces; Default: prod)
      • Enter the SCADA integration endpoint URL (format: https://<host>/api or https://<host>/ingest — platform will use this for telemetry push/pull)

      TURBINE TECHNICAL PARAMETERS

      • Primary turbine model identifier to lock for procurement (enter exact model name as used on POs)
      • Rated unit capacity in MW (numeric; Default: 3.6)
      • Rotor diameter in meters (numeric; Default: 120)

      COMMISSIONING & ACCEPTANCE CRITERIA

      • Availability acceptance threshold during the performance acceptance period (%) (numeric; Default: 97)
      • Performance acceptance period used for commissioning acceptance (days; Default: 30)
      • Power curve reference to use for acceptance tests Options: Manufacturer-declared power curve, Site-specific measured power curve, Third-party independent power curve

      SCADA, TELEMETRY & O&M HANDOVER

      • SCADA protocol for integration (select one) Options: IEC 61850, OPC-UA, MODBUS TCP, Proprietary OEM protocol, Other
      • List required telemetry channels (enter comma-separated exact channel names; e.g., wind_speed,rotor_speed,active_power,reactive_power)
      • Named role who will own the O&M handover (enter role title; e.g., 'Asset Manager' or 'O&M Lead')
    3. Construction & Commissioning

      Execute turbine delivery, balance-of-plant works, commissioning tests, and handover activities with clear owners and milestones.

    4. Interconnection & Safety Sign-Off

      Mandatory pre-energization gate: verify utility approvals, inspections, safety authorizations, and named-owner clearance before operation.

      Checklist items

      • Receive written Permission to Operate (PTO) from the utility or interconnection authority
      • Obtain final electrical inspection report from the authority having jurisdiction
      • Complete and archive Lockout/Tagout (LOTO) release records for energization work
      • Receive signed named-owner energization clearance
      • Verify completion and acceptance of core commissioning tests
      • Validate protective device and relay settings with test evidence
      • Confirm grounding and bonding verification report is complete
      • Confirm communications and telemetry handover to grid operator and owner operations
      • Confirm interconnection commercial and operational conditions are documented and met
      • Verify critical spare parts and initial O&M readiness items are on site or confirmed by PO
  6. Operational Success

    Track generation vs. modeled output, availability, warranty and service issues, and maintain a shared channel for enhancements and tickets.

    1. Operational Success

      Track generation vs. modeled output, availability, warranty and service issues, and maintain a shared channel for enhancements and tickets.

      Performance Reviews

      • Go-live Health Check
      • First Operational Measurement
      • 90-day Operational Acceptance Review
      • Quarterly Operational Business Review
      • Monthly Service Triage
      • Ensure warranty and recurrent failure modes are assigned corrective programs with monitoring checkpoints.
      • Update the shared ticket channel with prioritized service incidents and expected closure dates.
      • Restate acceptance criteria and numeric targets
      • Document pass/fail status for every acceptance criterion recorded in Solution Scope.
      • For any non-passing items, agree a remediation plan with explicit deadlines that will return the item to compliance.
      • Establish the post-acceptance operational review rhythm and the metrics each cadence will carry.
      • Publish the operational acceptance record showing pass/fail per criterion and link to the underlying data exports.
      • Create remediation tickets for failed criteria with target resolution dates and monitoring checkpoints.
      • Schedule the quarterly business review and recurring monthly triage meetings in the shared workspace.
      • Quarterly generation and capacity factor trends
      • Confirm quarterly performance against Solution Scope targets for generation and availability.
      • Prioritize the top operational backlog items and assign resolution timelines for the coming quarter.
      • Publish the quarterly performance dashboard with annotated variance explanations and recommended priorities.
      • Convert prioritized backlog items into specific tickets with target completion dates.
      • Initiate any required warranty claim actions with documentation and expected timelines.
      • Review critical open tickets and status
      • Reduce the number of critical open service tickets and shorten MTTR for priority issues.
      • Ensure all safety mitigations are documented and time-bound until permanent fixes are applied.
      • Identify and mitigate any procurement or parts delays blocking repairs.
      • Update the shared ticket channel with revised target dates for each critical ticket.
      • Raise procurement requests for any long-lead items and record expected delivery dates.
      • Schedule the next on-site technician visit for unresolved high-severity issues.
      • Re-confirm scope, success criteria, and owners
      • Confirm the plant is in monitored operational state and that core handover items are complete.
      • Document all critical open issues and agree remediation actions with target dates.
      • Ensure monitoring and alerting subscriptions are active for the buyer's operations team.
      • Publish a go-live validation report summarizing completed handover items and known issues.
      • Open tickets for each critical issue with target resolution dates and link to the shared ticket channel.
      • Enable and verify alert subscriptions for the buyer's nominated operations contacts.
      • Present period production and availability
      • Determine whether generation (MWh) and turbine availability percentage are tracking toward Solution Scope targets and identify the largest gaps.
      • Agree specific corrective actions with resolution dates to bring performance to acceptance levels.
      • Confirm telemetry and data integrity so future measurements are trustworthy.
      • Produce a gap analysis packet that links deviations to SCADA evidence and recommended fixes.
      • Schedule any required site inspections or component replacements and record target completion dates.
      • Ticket burn-down and MTTR trends
      • Telemetry and monitoring integrity review
      • Deployment and handover validation
      • Present outcome data against each criterion
      • Availability and downtime analysis
      • Warranty and service incident summary
      • Pass/fail determination per criterion
      • Diagnose gaps and root causes
      • Temporary mitigations and safety items
      • Telemetry and monitoring sanity check
      • Service and warranty issues summary
      • Formal acceptance decision and documentation
      • Early operational signals and usage patterns
      • Enhancements and ticket backlog triage
      • Service supply chain and procurement constraints
      • Financial operating indicators
      • Agree corrective actions and timeline to acceptance
      • Update the enhancement and patch schedule
      • Blockers, incidents, and immediate remediation plan
      • Remediation plan for any failed or conditional items
      • Agree ongoing operational cadence
    2. Tickets

      Tickets the customer raises land here once the journey is shared.

    3. Feedback

      Feedback from the customer lands here once the journey is shared.

First-Party AI ™

1-2 minutes please — Your AI agent is working

First-Party AI™ can make mistakes. Always check important information.