Industrial & Manufacturing Heavy Construction & Infrastructure Infrastructure & Capital Projects

Capital Project Delivery

Capital construction programs where procurement discipline, schedule certainty, and field execution determine delivery.

Example organizations in this space: Turner Construction Skanska Whiting-Turner Mortenson

This interactive experience is the shipped product itself — the same application code customers run in production, mounted read-only in your browser over a real sample journey. Not a video, not a mockup: because the demo and the product are one codebase, it can never drift from the real thing.

Inside this journey
  1. Pre-Construction

    Align stakeholders, validate constraints, and lock a delivery approach before formal scoping.

    1. Outcome & Risk Discovery

      Align on desired occupancy date, cost targets, stakeholder roles, site constraints, and the top schedule and budget risks that must be mitigated.

      Discovery Questions

      Setting the scene: your fixed date and why it matters

      • Tell me briefly how fixed your project's occupancy date is and why it cannot move
      • Describe your current target occupancy date and any contractual or financial penalties tied to missing your date
      • How many months of schedule float do you believe your program actually has before your occupancy date would slip Options: 0 months, 1-2 months, 3-4 months, 5-6 months, More than 6 months
      • Which cost target structure has your board approved for your project Options: Firm guaranteed maximum price, Target budget with specified contingency, Board-approved range, No formal cost target yet
      • Who on your team holds the final sign-off authority for both budget and the occupancy date Options: CFO/Finance leader, VP of Capital Planning, Director of Facilities, Project Manager, Board or committee, Other
      • Pinpoint any external deadline or contractual penalty tied to your occupancy date that would force you to halt the project if missed

      Where the schedule could break: the single event that stops everything

      • If a single construction constraint on your site forced the occupancy date to slip, which constraint would that be
      • Name the activities you believe currently sit on your critical path, and select those that apply Options: Structural concrete pour, Structural steel erection, Long-lead equipment delivery, MEP rough-in, Testing and commissioning, Site utility relocation, Other
      • When in past projects on your campus did you see the largest schedule delays, and what specifically caused them
      • Could you quantify the schedule impact in weeks if your primary structural trade were delayed by one month Options: Under 2 weeks, 2-4 weeks, 4-8 weeks, More than 8 weeks
      • Who on your team would be the first person to escalate to if your schedule slipped by more than four weeks Options: Project Manager, Director of Facilities, VP Capital Planning, CFO/Finance leader, Other

      Budget boundaries that cannot bend

      • Which single budget shortfall would force you to value-engineer the project and compromise core functionality
      • Provide the percentage contingency you need to see before you would feel comfortable signing a construction contract Options: 0-3%, 4-7%, 8-12%, 13% or more
      • Describe any line items or functional areas your team considers sacrosanct and not open to value engineering
      • Estimate how often projects in your portfolio have exceeded initial budgets and by which typical percent Options: Rarely, under 5%, Occasionally, 5-10%, Often, 10-20%, Frequently, over 20%
      • Are there external funding constraints, revenue-recognition dates, or bond covenants tied to your occupancy date that would limit schedule flexibility Options: Yes, strict and binding, Yes, manageable with waiver, No binding constraints, Unsure

      Who's driving decisions and where approvals get stuck

      • Identify who in your governance structure can veto a contractor recommendation and how quickly that person or group typically decides
      • Walk me through your approval path from preliminary estimate to sign-off on GMP or contract award
      • List the external reviewers or committees that typically extend review cycles or introduce new scope late in preconstruction Options: Board committee, Clinical leadership/department heads, Facilities operations, Finance team, Compliance/regulatory review, Insurance underwriter, Other
      • Would staff turnover in particular roles create the biggest loss of continuity for this program, and which roles are those Options: Project Manager, Facilities Director, Design lead, Finance/estimating contact, Other
      • How often does your team bring in external constructability reviewers before 60 percent design, and who coordinates that Options: Always before 60%, Sometimes before 60%, Rarely before 60%, Never

      Site realities that change what you can promise

      • Pinpoint the single site constraint that would force a phased delivery instead of full access
      • Name the permits or approvals most likely to delay groundbreak on your site, and indicate who currently owns each application Options: Building permit, Environmental/egress approvals, Utility connection permits, Traffic/lane closure approvals, Health or sterile environment approvals, Other
      • When will your occupied-area constraints require night or weekend work to meet the occupancy date Options: Not required, Intermittently during peak activities, Regularly for several months, Unknown
      • Could restricted site access windows, such as dock availability or campus road closures, compress your critical-path activities Options: Yes, significantly, Yes, moderately, No, Unsure
      • Provide any noise, vibration, or sterile-environment restrictions that will limit weekday work in occupied areas

      Top risks that would stop you from signing

      • Identify the top three risks that, if realized, would cause you to pause or cancel the project Options: Budget overrun from scope gap, Long-lead equipment delay, Structural trade delay, Regulatory approval failure, Bonding or insurer refusal, Other
      • Explain the mitigation your team currently has budgeted or planned for each of those risks
      • If bonding, insurance, or surety requirements shifted unfavorably, which specific requirement would most likely block awarding a contract Options: Bonding limit too low, Insurer exclusions for work type, Premium increases make it unaffordable, No material impact expected
      • Confirm who on your team owns the day-to-day risk register and who is enabled to close preconstruction risk items Options: Project Manager, Risk Manager/PMO, Director of Facilities, VP Capital Planning, Other
      • Rate your confidence from 1 to 5 that your top schedule and budget risks are avoidable with additional preconstruction effort Options: 1, 2, 3, 4, 5

      Other options you are weighing

      • List the alternatives you are actively considering to deliver this project, including internal delivery or incumbent contractors Options: Incumbent contractor, Internal delivery by in-house PM/ops, Traditional design-bid-build GC, Design-build with single-source contractor, Construction manager at risk, Delay/postpone the project, Other
      • Choose the option you are most likely to pursue if nothing changes, and briefly say why Options: Stay with incumbent, Go internal, Select a new GC through RFP, Shift delivery method (DB/CMAR), Delay project, Other
      • To stay with your current approach, what would have to be true about cost, schedule, or risk allocation
      • Has anyone on your team proposed solving delivery internally without an outside partner, and if so who recommended it and why Options: Yes, recommended and viable, Yes, recommended but not viable, No internal proposal, Unsure
      • Would switching to an at-risk delivery model with self-perform capability change how you prioritize schedule certainty versus cost Options: Prioritize schedule over cost, Prioritize cost over schedule, Need a balance of both, Unsure

      Operational readiness: gating items that must be true before work starts

      • Outline the hard prerequisites that, if unmet, will prevent construction mobilization even if a contract is signed
      • Detail whether your team has named owners for permits, long-lead procurement, and site-access coordination, and list their roles
      • Are your project data feeds, document repositories, and schedules accessible for sharing with an external delivery partner Options: Yes, fully accessible, Partially accessible, No, not accessible, Planned but not ready
      • Estimate the minimum bonding or financial capacity you would require from a contractor to feel secure on a project of this scale Options: Under $5M, $5M to $25M, $25M to $100M, Over $100M, Not sure
      • Give the target month or date by which key permits must be in hand to allow major mobilization on your site

      Deal accelerators and deal stoppers: what would make you sign tomorrow or walk away

      • Imagine a single answer today could get your team to sign within 30 days, what would that answer need to prove
      • Choose the one document or commitment that would accelerate award this month Options: Firm GMP proposal, Bonding commitment letter, Accepted schedule baseline, Detailed reconciled cost model, Signed governance and change-order process, Other
      • Specify the fatal flaw in a contractor proposal that would make you halt negotiations immediately
      • Confirm whether you are authorized to recommend award, or whether final approval sits with another person or committee Options: I can recommend only, I can approve, Final approval by board or committee, Other
      • Specify your preferred turnaround time for receiving a revised workplan and pricing after our preconstruction sessions conclude Options: Within 1 week, 1-2 weeks, 3-4 weeks, More than 4 weeks
    2. Preconstruction Experience

      Walk through how embedded estimating, constructability review, phased logistics, and self-perform structural work will protect the budget and fixed occupancy date using the buyer's project context.

      Solution Experience

      • Preconstruction Experience Session
      • Confirm the current state and its cost
      • You confirm the demonstrated embedded estimating workflow eliminates the budget surprises you described.
      • Deliver a preliminary embedded estimate comparing the current budget to the estimate of record within 7 business days.
      • You accept that the shown constructability and logistics mitigations materially reduce schedule risk to the fixed occupancy date.
      • Proof: Embedded estimating against your numbers
      • Produce a draft phased logistics plan that maps access windows and occupied-area protections for the first construction phase within 10 business days.
      • Proof: Constructability review and risk mitigation
      • Provide the latest design files, occupancy constraints, and key milestone dates for use in the estimate and logistics plan.
      • You agree on the specific deliverables and timing required to produce a baseline estimate and phased logistics plan for decision.
      • Proof: Phased logistics and occupied-area sequencing
      • Identify and confirm the acceptance criteria you will use to sign off the preconstruction baseline and the fixed occupancy date.
      • Proof: Self-perform structural control of the critical path
      • Validate the outcome with explicit confirmation
      • Agree next evidence and commitments
      • Preconstruction Experience Session
      • Preconstruction Experience Deck
      • Preconstruction Solution Brief
      • meeting
      • slides
      • document
  2. Project Scope

    Define deliverables, phasing, self-perform trade boundaries, acceptance criteria, and exclusions that set the project baseline.

    Scope Configuration

    • Embed Estimating Team During Design to Lock Budget
    • Deliver Guaranteed Maximum Price (GMP) Contract Package
    • Deliver Baseline CPM Schedule and Monthly Updates
    • Implement Cost Controls and Change Order Management
    • Procure Long-Lead Equipment and Vendor Coordination
    • Manage Subcontractor Buyout and Contracting
    • Self-Perform Concrete Foundations and Structural Slabs
    • Self-Perform Structural Steel Erection
    • Self-Perform Finish Carpentry and Interior Framing
    • Phased Construction Execution Around Occupied Facilities
    • Install Temporary Life-Safety and Infection-Control Barriers
    • Commissioning and Systems Turnover to Owner
    • Deliver As-Built Drawings, O&M, and Warranty Handover

    Scope Questions

    Embed Estimating Team During Design to Lock Budget

    • For embedding an estimating team, during which design milestone should we first deliver a reconciled cost model (schematic, 50% construction documents, 100% construction documents)? Options: Schematic design, 50% construction documents, 100% construction documents, Other (describe)
    • For the embedded estimating scope, which cost deliverables do you require (select all that apply)? Options: Line-item trade estimate, Assemblies/unit-cost model, Cost reconciliation to owner's budget, Risk/contingency log, Value-engineering alternatives
    • For the estimate inputs, provide the design package reference we should use (e.g., file name of 50% CD set, shared folder link, or drawing revision number).
    • For modeling cost drivers, list project-specific items to be quantified (examples: MRI shielding, cleanroom finishes, rooftop AHU structural upgrades).
    • For cost governance, indicate the threshold that should trigger a formal value-engineering review (e.g., 5% over baseline, $500,000 over baseline). Options: 5% over baseline, 10% over baseline, Specific dollar amount (specify below), No automatic threshold
    • For approvals, who in your organization has final sign-off authority for reconciled estimates (role and contact preferred)?

    Deliver Guaranteed Maximum Price (GMP) Contract Package

    • Regarding the GMP contract package, which contract form do you expect to execute (owner-directed GMP amendment, guaranteed maximum price exhibit to CM at-risk agreement, other)? Options: GMP amendment to CM/GC agreement, GMP exhibit within new contract, Fixed-price lump sum, Need to discuss/decide
    • Regarding GMP inclusions, which of these must be explicitly priced inside the GMP (select all that apply)? Options: Owner-furnished equipment installation, Testing and balancing (TAB), Permit fees and inspection costs, Contingency and allowances, Temporary works and scaffolding
    • Regarding risk transfer, provide any bonding or insurer documentation requirement we must meet (e.g., bond capacity letter, performance bond percentage).
    • Regarding the GMP schedule tie-in, specify the contract milestone that must align with GMP pricing (e.g., guaranteed occupancy date, turnover milestone, phased occupancy date). Options: Single final occupancy date, Phased occupancy dates, Critical milestone (specify below), No fixed occupancy required
    • Regarding exclusions, list items you expect to be excluded from the GMP (examples: owner IT systems, FF&E, hazardous-material abatement beyond allowance).
    • Regarding acceptance evidence for the GMP package, which of these will you accept as final (signed GMP amendment, reconciled line-item GMP estimate, and certified schedule baseline)? Options: Signed GMP amendment plus reconciled line-item estimate, Reconciled line-item estimate and certified schedule baseline, Need to define alternate acceptance evidence

    Deliver Baseline CPM Schedule and Monthly Updates

    • For the baseline CPM schedule, which software and file deliverable do you require (Primavera P6 XER, Microsoft Project MPP, baseline PDF with critical-path annotation)? Options: Primavera P6 (XER), MS Project (MPP), Baseline PDF with critical-path, Other (specify)
    • For schedule granularity, indicate the level of detail you need on the baseline critical path (day-level activities for structural erection, weekly-level for FF&E, or custom). Options: Day-level for major trades, Weekly-level only, Mixed granularity (specify)
    • For long-lead integration, list any long-lead work packages that must be in the CPM baseline (examples: rooftop AHU series, MRI systems, chillers).
    • For monthly schedule updates, specify the format of variance reporting you prefer (updated CPM file, one-page critical-path dashboard, recovery plan for delays). Options: Updated CPM file, One-page critical-path dashboard, Recovery plan and variance narrative, Combination of the above
    • For integration with controls, identify the named owner/system that must receive schedule milestones (e.g., your project controls PM, owner's commissioning lead).
    • For schedule acceptance, what evidence will confirm the baseline is approved (signed schedule acceptance form, approved XER file, or governance meeting minutes)? Options: Signed schedule acceptance form, Approved XER/MPP file with baseline stamp, Governance meeting minutes approving baseline, Need to define acceptance evidence

    Implement Cost Controls and Change Order Management

    • For cost control, which reporting cadence do you require for earned-value and forecast updates (monthly, bi-weekly, or ad hoc on milestone completion)? Options: Monthly, Bi-weekly, Ad hoc on milestone
    • For change-order workflow, describe the documentation package you require to approve a change (RFI, pricing proposal, updated scope page, and ECN log).
    • For authorization thresholds, specify who in your organization can approve change orders by dollar band (role and threshold).
    • For contingency management, indicate whether you require a project-level contingency log tied to the estimate and identify desired update frequency. Options: Yes, tie to estimate and update monthly, Yes, tie to estimate and update per milestone, No formal contingency log required
    • For accounting integration, which financial artifact must change-order data reconcile with (your ERP project code, CIP ledger account, or owner's cost-control spreadsheet)? Options: ERP project code, CIP ledger account, Owner's cost-control spreadsheet, Other (specify)
    • For auditability, list any compliance or reporting standards we must meet for change orders (examples: AIA contract exhibits, governmental grant reporting, audit-ready backup).

    Procure Long-Lead Equipment and Vendor Coordination

    • For long-lead procurement, list the specific equipment items you already know are long lead (examples: MRI units, rooftop chillers, custom AHUs, switchgear).
    • For vendor coordination, indicate whether vendors will provide factory acceptance test (FAT) documentation and if FAT dates must be integrated into the site CPM. Options: Vendors provide FAT and dates must be tied to CPM, Vendors provide FAT but dates are advisory, Vendors do not provide FAT
    • For lead-time confirmation, what level of vendor delivery certainty do you require before releasing long-lead purchase orders (manufacturer lead-time letter, deposit and PO, full paid order)? Options: Manufacturer lead-time letter, Deposit and PO, Full paid order, Flexible depending on item
    • For installation interfaces, identify critical integration points for long-lead equipment (structural slab openings, dedicated crane or rigging windows, electrical feeder routing).
    • For logistics, specify any site constraints affecting deliveries (off-hour deliveries only, campus delivery windows, restricted laydown area). Options: Off-hour deliveries required, Regular business hours allowed, Campus delivery windows apply, Other (specify)
    • For vendor documentation, which artifacts must be delivered before site installation (cut sheets, shop drawings, submittal register entries, test reports)? Options: Cut sheets, Shop drawings, Submittal register entries, Test reports, All of the above

    Manage Subcontractor Buyout and Contracting

    • For subcontractor buyout, which prequalification documents do you require from trade partners (bonding certificate, safety EMR/TRIR, references on comparable hospitals/universities)? Options: Bonding certificate, Safety EMR/TRIR, Relevant references, Insurance certificate, All of the above
    • For contracting terms, indicate required subcontract clauses we must include (liquidated damages tied to occupancy date, performance milestones, owner indemnity).
    • For payment terms, which subcontract payment structure is preferred (progress draws against schedule of values, milestone payments, lump-sum upon completion)? Options: Progress draws against schedule of values, Milestone payments, Lump-sum on completion, Hybrid
    • For buyout timing, specify the date by which critical subcontract packages must be executed to protect the schedule (e.g., structural steel contract by X date).
    • For dispute avoidance, list any owner-required subcontract provisions (e.g., no-damages-for-delay waiver, dispute resolution forum).
    • For subcontractor scope clarity, which deliverable should be included in each subcontract package (detailed scope attachment, submittal schedule, coordination matrix)? Options: Detailed scope attachment, Submittal schedule, Coordination matrix, All of the above

    Self-Perform Concrete Foundations and Structural Slabs

    • For self-performing concrete, identify the foundation types involved (spread footings, pile caps, mat slab, post-tension slab) and which apply to your project. Options: Spread footings, Pile caps, Mat slab, Post-tension slab, Combination
    • For mixture design, which concrete specifications must be met (compressive strength psi at 28 days, slump range, admixture restrictions)?
    • For slab-on-grade schedule impacts, indicate any owner constraints on early slab curing or on-site concrete batching (temperature control, night pours). Options: Temperature control required, Night pours acceptable, No special constraints, Other (specify)
    • For coordination with other trades, list slab openings or embedded items we must coordinate (under-slab MEP sleeves, post-installed anchors, embedded sleeves for medical gases).
    • For quality evidence, which deliverables do you expect for concrete (mill certificates, compressive test reports, as-built reinforcement layouts)? Options: Mill certificates, Compressive test reports, As-built reinforcement layouts, All of the above
    • For lifting and schedule, specify any crane or heavy-rigging windows that affect foundation pours or large slab pours.

    Self-Perform Structural Steel Erection

    • For structural steel erection, state the erection sequence constraints tied to occupancy or adjacent operations (e.g., keep existing hospital wing open, maintain patient access).
    • For steel deliveries, what site receiving restrictions exist (time-of-day limits, staged deliveries to on-campus laydown, max truck length)? Options: Time-of-day limits, Staged deliveries, No restrictions, Other (specify)
    • For erection quality, which documents must be submitted before erection begins (shop drawings, erector qualifications, bolting torque procedures)? Options: Shop drawings, Erector qualifications, Bolting torque procedures, Lift plans
    • For heavy lifts, identify any specialty crane or rigging requirements (pick list: lattice boom, crawler crane, multi-crane lifts) and required lift plans.
    • For schedule resilience, describe how we should prioritize steel sequences to protect the fixed occupancy date (e.g., structural-first critical-path focus, early enclosure).
    • For safety metrics, do you require erector safety documentation including EMR and TRIR as part of scope acceptance? Options: Yes, EMR and TRIR required, No, not required, Provide on request

    Self-Perform Finish Carpentry and Interior Framing

    • For interior finish work, list the finishing standards or mockup requirements we must meet (example: millwork mockup, casework elevations for clinical rooms).
    • For sequencing, indicate how finish carpentry must be phased relative to MEP rough-in and testing in occupied areas. Options: After 100% MEP rough-in, After MEP testing in each zone, Flexible per zone
    • For acoustical and infection control, specify finish materials with special requirements (e.g., cleanable surfaces for ORs, acoustic panels for labs).
    • For submittals, which artifacts must be provided before fabrication (shop drawings, hardware schedules, finish samples)? Options: Shop drawings, Hardware schedules, Finish samples, All of the above
    • For warranty handover, what minimum warranty duration do you expect on millwork and interior framing (e.g., 1 year, 2 years)? Options: 1 year, 2 years, Custom (specify)
    • For occupied-area constraints, describe any access or staging restrictions for interior carpentry in clinical spaces (night work only, decant rooms, limited dust tolerance).

    Phased Construction Execution Around Occupied Facilities

    • For phased execution, provide the fixed occupancy milestones we must protect (e.g., hospital tower first-bed occupancy date, semester start date).
    • For occupant protections, identify critical areas requiring continuous operations (example: emergency department, clean labs, production lines) and any non-work hours constraints.
    • For sequencing, which phase handover artifacts must be delivered at each phase (punchlist completion, temporary certificate of occupancy, partial MEP commissioning reports)? Options: Punchlist completion, Temporary certificate of occupancy, Partial MEP commissioning reports, Other (specify)
    • For logistics in phased work, describe required site access protocols during occupied phases (staging areas, security escorts, designated delivery routes).
    • For noise and vibration controls, what vendor-specific or owner-imposed thresholds must we meet (peak dB limits near patient rooms, vibration limits for sensitive equipment)?
    • For governance, who on your side will be the phase acceptance authority for each phased turnover (role and contact preferred)?
  3. Mutual Commit

    Finalize commercial and contractual terms, governance, milestones, bonding/capacity confirmation, and the change-order/acceptance process.

    Agreement Modules

    • Master Services Agreement (MSA)
    • Statement of Work (SOW)
    • Guaranteed Maximum Price (GMP) / At-Risk Amendment
    • Project Milestones & Payment Schedule
    • Performance and Payment Bonds
    • Insurance Certificate & Indemnity Schedule
    • Change Order Procedure
    • Acceptance & Commissioning Criteria
    • Notice to Proceed (NTP)
    • Governance & Escalation Plan
    • Trade Boundary & Self-Perform Scope Addendum
    • Lien Waiver & Final Release Forms
    • Regulatory Compliance Addendum (conditional)
  4. Project Execution

    Operationalize construction with readiness checks, configuration locks, execution, and formal acceptance.

    1. Pre-Deployment Readiness

      Capture concrete readiness facts — site access windows, phasing dates, occupied-area constraints, key permits, and named owners required to start construction.

      Pre-Deployment Questions

      Environment and site access

      • Primary construction site(s) and single point of contact for site access (name and role). We will use this to schedule escorts, gate passes, and initial mobilization.
      • Is an agreed daily/weekly site access schedule documented (work hours, night work, weekend allowance, and holiday restrictions)? (so we can plan crew shifts and deliveries) Options: Yes — standard weekday hours only, Yes — includes nights, Yes — weekends allowed, No — access not finalized, Other (explain below)
      • Are temporary utilities required for mobilization (temporary power, water, site communications)? Select current state and note who will arrange them. Options: Confirmed and onsite, Confirmed but requires coordination before mobilization, Planned but not arranged, Not required

      People and ownership

      • Named owners for these critical start tasks: site access approval, permit coordination, security escort, and IT/MEP shutdown approvals. (List name and role for each — we will assign tasks and escalation paths)
      • Is there a single on-site buyer representative authorized to approve start-of-work per phase (so the seller knows who can sign off to mobilize)? Options: Yes — single named on-site rep, No — approvals require committee or multiple sign-offs, Other (explain below)

      Permits and compliance

      • Which of the following permits/approvals are already approved? (select all that apply — we need this to schedule inspections and first inspections on the critical path) Options: Building permit, Trade permits (electrical/mechanical/plumbing), Fire marshal approval, Environmental/erosion control permit, Utility service agreements (temporary/ permanent), None of the above
      • Which required permits/approvals are still outstanding, and what is the expected approval date for each? (enter permit type and expected approval date — so we can sequence mobilization and inspections)

      Timing and constraints

      • Target first mobilization date for phase 1 (or 'TBD'). This date will drive procurement, crew assignment, and baseline schedule creation.
      • Confirmed phasing and handover dates for each occupied area or construction phase (list phase name and start/handover dates). We will use these to lock schedule baselines and phased logistics.
      • Are there hard blackout dates or occupied-area constraints (e.g., patient move-in windows, academic exam periods, production shutdowns)? If yes, list date ranges and the areas affected. Options: No hard blackouts, Yes — limited date ranges and areas (detail below), Yes — ongoing occupancy restrictions across multiple areas (detail below)
    2. Construction Logistics & Configuration

      Lock schedule baselines, phased logistics, critical-path resource assignments, procurement lead times, and technical configuration parameters for site execution.

      Configuration Details

      Locking the Master Schedule — Environments & Baseline IDs

      • Enter the production schedule instance name used in your scheduling tool (exact string). Default: 'Master Schedule'.
      • Provide the baseline schedule file or URL (format: https://... or network path like \\server\path\Schedule.mpp). The deployment reads this exact string.

      Schedule Baseline Controls

      • Select the schedule baseline approval method the deployment should enforce. Default: 'Schedule system approval flag (your scheduling tool)'. Options: Schedule system approval flag (your scheduling tool), Signed baseline document (PDF), Email approval from buyer project manager, Platform approval workflow
      • Baseline revision lock window in days (integer). Default: 14 — after this many days before occupancy the baseline is locked against major changes.

      Phased Logistics Configuration

      • Number of construction phases to configure in the platform (integer). Default: 3.
      • Phase logistics plan owner (enter role or team name exactly as used internally, e.g., 'Site Logistics Lead').

      Procurement Lead Times & Integrations

      • Default procurement lead time for long-lead items in days (integer). Default: 90.
      • Procurement system identifier (enter system name or integration ID; do NOT paste credentials — e.g., 'ERP-Procure-US' or 'ProcureSys-PRJ1').

      Technical Configuration for Site Execution

      • Site technical configuration document location (format: https://... or network path; enter the exact path or URL your team uses).
      • Who owns critical-path resources for execution (select one). Default: 'Seller self-perform controls critical-path resources'. Options: Seller self-perform controls critical-path resources, Seller coordinates subcontractor critical-path resources, Buyer provides/assigns critical-path resources
    3. Construction Execution

      Manage the construction work with a living schedule, safety oversight, procurement coordination, and phased sequencing against the agreed baseline.

    4. Commissioning & Occupancy Acceptance

      Formal acceptance gate confirming commissioning, punchlist completion, regulatory approvals, and signed occupancy/turnover prior to final billing.

      Checklist items

      • Receive and accept final commissioning report
      • Obtain signed commissioning test records for all critical systems
      • Verify punchlist completion and get final punchlist sign-off
      • Secure written regulatory approvals and occupancy permit
      • Confirm utility/energization permissions and LOTO documentation
      • Deliver and have buyer accept as-built drawings and O&M manuals
      • Complete operator training and obtain training sign-off
      • Provide final closeout and warranty documentation package
      • Submit final payment package and required financial closeout documents
      • Obtain signed occupancy/turnover acceptance certificate
  5. Post-Occupancy Success

    Validate occupancy outcomes against success criteria, review cost and schedule performance, and maintain a shared channel for warranty issues and enhancements.

    Success Reviews

    • Post-Occupancy Health Check (weeks 1-4)
    • First Performance Measurement (weeks 4-10)
    • 90-Day Operational Validation (around day 90)
    • Quarterly Operational Review
    • Year-One Realization Review

    Issues & Enhancements

    • Cost-to-complete forecast reconciled and any remaining exposures assigned to actions for the final account.
    • Provide a short cost-to-complete update reflecting corrective actions and any reserve usage.
    • Present 90-day outcome data
    • A definitive, timebound remediation plan exists for all outstanding punchlist and warranty items, with target close dates.
    • A reconciled view of cost and schedule performance to date is recorded for use in final account preparation.
    • Publish the 90-day remediation schedule and link each item to the recorded acceptance criteria in Project Scope.
    • Deliver a warranty SLA proposal that sets target days-to-close and escalation steps for recurring issues.
    • Warranty backlog trend
    • Warranty backlog is reducing and average days-to-close meet the SLA agreed in the 90-day plan.
    • Re-confirm success criteria and owners
    • Produce the quarterly warranty backlog report with trend charts and top recurring issues.
    • Update the final account forecast and list any pending change-order evidence required for closure.
    • 12-month cost and schedule realization
    • Final realization documented showing cost variance and schedule variance against the original targets recorded in Outcome & Risk Discovery and Project Scope.
    • Institutional handoff completed with documentation, lessons learned, and a standing warranty/enhancement channel established.
    • Publish the year-one realization report including cost and schedule variance analysis and lessons learned.
    • Archive project closeout records and confirm the retention location and access for your operations team.
    • All critical site access, safety, and handover blockers identified, with owners and remediation dates assigned.
    • Shared warranty and punchlist channel created and accessible to your operations team.
    • Publish the initial remediation log with owners and due dates to the shared channel.
    • Create the warranty ticketing feed and confirm how tickets will be triaged and escalated.
    • Present first performance data
    • Determine whether occupancy date variance and punchlist completion rate are trending to the targets recorded in Outcome & Risk Discovery and Project Scope.
    • Named remediation actions and dates agreed for each metric that is off-target.
    • Publish a corrective action plan with milestones for punchlist closure and any schedule recovery tasks.
    • Deployment and handover validation
    • Warranty resolution performance
    • Operational performance review
    • Root-cause analysis for gaps
    • Operational outcomes and uptime
    • Lessons learned and process improvements
    • Cost and schedule performance snapshot
    • Cost-to-complete and final account update
    • Agree corrective actions and schedule
    • Early operational signals
    • Confirm timeline to next validation
    • Operational risks and enhancements backlog
    • Agree final remediation and warranty timelines
    • Open issues and blockers
    • Long-term warranty and enhancements plan
    • Agree immediate remediation actions
First-Party AI

1-2 minutes please — Your AI agent is working

First-Party AI™ can make mistakes. Always check important information.