Greenfield Site Preparation
Complex deployments where integration, safety, and operational handoff determine production success.
This interactive experience is the shipped product itself — the same application code customers run in production, mounted read-only in your browser over a real sample journey. Not a video, not a mockup: because the demo and the product are one codebase, it can never drift from the real thing.
Inside this journey
-
Project Discovery
Align on the buyer's objectives, timeline constraints, site-specific risks, stakeholders, and success signals for the greenfield decision.
Discovery Questions
Let's orient on the site and the business case
- Tell me about the greenfield parcel you are evaluating and the primary business driver for choosing it
- Walk me through the go/no-go timeline for land purchase, due diligence milestones, and any external deadlines tied to the decision
- How many acres are in the parcel and what portion do you expect to develop in the first phase
- Which internal metric will determine whether leadership considers this site a success
- Who on your team is the primary owner of the site selection decision and who else influences it
Where the decision really breaks — timing, cost, or surprises
- If subsurface surprises forced a six-month delay and a 20% cost increase, would you proceed with the land purchase
- Identify the top three operational consequences if the building pad misses the equipment installation date
- On what fixed date must the pad be ready for your critical path activities, for example equipment set or foundation start
- Rate how you prioritize cost, schedule, and regulatory certainty when making the purchase decision
- Describe a past project where an unexpected site condition changed your outcome, including the cost or schedule impact
- Which single site risk would make you walk away from the purchase immediately
Point to the schedule assumption you trust least
- Point to the schedule assumption you trust least and explain why
- When is the land closing targeted and how firm is that date
- How many critical milestones must be met before mobilization, for example final geotech, site survey, permits, or utility agreements
- Who must sign off to authorize mobilization to the site and what will they require to say yes
- If a required permit slips by more than 8 weeks, what is the single decision you would make about the project timeline
The ground truth — subsurface and environmental blind spots
- Tell the last time a geotechnical or environmental finding changed feasibility on a site you control, and what it cost in time or money
- To what depth were borings performed for this parcel, or if no borings exist, indicate that status
- Which environmental investigations have been completed, select all that apply
- If widespread shallow rock or unsuitable soils are discovered across the pad, how flexible is your contingency budget expressed as a percentage
- Which regulatory approval, if delayed beyond 12 weeks, would stop the project
The other paths you're considering
- What alternatives to hiring an external site development partner are you actively evaluating
- What would have to be true about your current approach for you to stay with it instead of switching to an outside partner
- Has anyone inside your organization proposed solving site preparation fully in-house, and if so, who would lead that effort
- Which criteria would cause you to favor an incumbent over a new partner
- If an internal option can deliver a similar schedule but at 15–20% higher cost, which would you choose
Practical gates — permits, utilities, and who does what
- Point to any hard gating constraint that must be resolved before mobilization on your target schedule
- Which specific permits are outstanding and at what stage are they
- Who on your side will own utility coordination and municipal negotiations
- Does your team have a named owner for survey baselines and geotechnical deliverables
- If the city requires an easement negotiation that adds 10 weeks, what is your fallback plan
How you will accept the work — measurable and non-negotiable
- If we delivered the pad on time but with unresolved punch list items, would you accept it or delay final acceptance
- List the measurable acceptance criteria you require for final billing and turnover, select all that apply
- Which single acceptance criterion would you refuse to compromise on
- Are there any third-party inspectors or municipal signoffs that must be present at handover
- If acceptance is contingent on a third-party schedule, what maximum delay is acceptable before you stop the project
Budget guardrails, contingencies, and contract triggers
- Which payment milestone or mobilization trigger is most likely to block approval if it is unacceptable
- What is your target budget range for overall site preparation, select the closest band
- If contingency needs exceed 15%, would you pause negotiations, renegotiate scope, or accept the increase
- Which risk allocation arrangement do you prefer for unknown subsurface conditions
- If a vendor requires a mobilization deposit greater than 10% of contract value, would that be acceptable
Who moves this forward inside your organization
- Who in your leadership can veto this project and on what basis would they do so
- Walk me through the internal approval steps from the project owner to final sign-off, including procurement and finance involvement
- Which stakeholders will require tailored deliverables from the feasibility assessment, for example CFO wants cost ranges, operations wants schedule certainty
- At what point in the evaluation would you be comfortable giving authority to proceed to a single vendor
- Which internal resource constraints could slow the decision even if the feasibility numbers look good
If the feasibility study delivers, what happens next
- If the feasibility assessment confirms cost and schedule within your target, what stops you from signing a contract that same week
- Which deliverable from the assessment would most accelerate your ability to commit, choose one
- How soon do you expect to review the feasibility deliverables and who will attend that review
- What would you like the seller to prepare before the kickoff to make the assessment productive
- Are you ready to schedule an on-site kickoff meeting within the next two weeks if we agree scope and price
-
Feasibility Workshop
Walk through how the site-preparation program addresses cost, schedule, geotechnical uncertainty, permitting, and utility coordination using the buyer's site context.
Solution Experience
- Feasibility Workshop, Site-Preparation Program
- Confirm the current state and cost of failure
- You confirm the documented current-state consequences match your exposure to schedule and budget risk.
- Provide existing geotechnical reports, environmental surveys, and survey baselines for the parcel before the follow-up feasibility deliverable.
- You confirm the geotechnical approach and contingency logic would materially reduce subsurface uncertainty for your parcel.
- Geotechnical risk proof using your site data
- Deliver a site-specific feasibility estimate and schedule with identified risk allowances and recommended next investigations within 7 business days.
- Confirm the required pad delivery date and the acceptance criteria that will define on-time completion.
- You confirm the permitting and utility coordination plan provides a credible path to the pad delivery date or identify the gap that remains.
- Permitting and environmental mitigation proof
- Utility coordination and critical-path timeline proof
- You agree on the specific evidence and deliverables needed next to reach a go/no-go recommendation on the parcel.
- Propose a mobilization trigger and payment milestone structure tied to the agreed investigation outcomes and permit milestones.
- Cost and schedule tradeoffs tied to acceptance criteria
- Validate alignment with your needs
- Feasibility Workshop, Site-Preparation Program
- Feasibility Workshop Deck
- Feasibility Workshop Brief
- meeting
- slides
- document
-
Site Scope & Deliverables
Define earthwork, drainage, utility work, environmental mitigation, access roads, schedule milestones, responsibilities, and acceptance criteria.
Scope Configuration
- Site Clearing and Vegetation Removal
- Mass Earthwork (Cut, Fill, Rebalance)
- Rock Excavation and Controlled Blasting
- Pad Subgrade Preparation and Compaction
- Temporary Dewatering and Groundwater Control
- Underground Utility Trenching and Installation
- Perform Municipal Utility Tie‑ins
- Stormwater Infrastructure Construction (BMPs, Basins, Pipes)
- Erosion Control and Sediment Management Installation
- Wetland Mitigation and Habitat Restoration Works
- Access Road and Construction Entrance Buildout
- Foundations and Shallow Footing Construction
- Final Grading and Site Cleanup
Scope Questions
Site Clearing and Vegetation Removal
- Provide the acreage and the site plan reference for areas to be cleared (attach topo or parcel map if available).
- Identify any trees, protected species habitat, or no‑touch zones noted on the ecological survey or jurisdictional wetland delineation.
- List your preferred disposal or reuse method for cleared biomass and stumps per the local solid waste or C&D recycling rules.
- Specify seasonal or timing constraints for clearing referenced on the environmental memo (e.g., bird nesting window, breeding season).
- Confirm access limitations shown on the site plan or easement exhibits that could restrict clearing equipment size or haul routes.
- Describe erosion and sediment controls you expect during clearing as called out in the draft SWPPP or local ordinance.
Mass Earthwork (Cut, Fill, Rebalance)
- Provide the earthwork target volumes or the cut/fill balance from your grading plan (cubic yards), or indicate if only contour plan is available.
- Estimate acceptable haul distance to onsite borrow or offsite disposal and reference the borrow/source permit or quarry spec if known.
- List the maximum allowable heavy equipment axle loads and any roadway weight limits along proposed haul routes per local DOT/ROW notes.
- Specify the cut/fill slope limits and benching requirements shown on the geotechnical report or grading detail.
- Indicate the compaction standard expected for engineered fills (reference target density and standard, e.g., 95% modified Proctor ASTM D1557).
- Describe traffic control or permitting needs for offsite haul (local hauling windows, overweight permits, truck staging areas) referenced from the traffic management plan.
Rock Excavation and Controlled Blasting
- Provide the geotechnical or borings log indication of rock depth, rock type, and estimated rock volumes for blasting estimation.
- Identify any structures, utilities, or sensitive receptors within 500 feet that require a pre‑blast survey or vibration limits per local ordinance.
- Specify required blast vibration or airblast limits from the jurisdiction or owner standard (e.g., PPV mm/s or decibels).
- List the blast notification and permitting steps you expect (local blasting permit, pre‑blast survey, neighbor notifications).
- Describe rock excavation disposal strategy and testing requirements for reuse or offsite acceptance (e.g., aggregate spec, TCLP testing).
- Indicate if controlled blasting is restricted by time‑of‑day or seasonal limits on the project permit or local code.
Pad Subgrade Preparation and Compaction
- Provide the target pad elevation tolerance relative to the structural slab elevation shown on the civil/site plan (inches).
- Specify the compaction acceptance criteria for pad subgrade including test method and threshold (example: 95% modified Proctor ASTM D1557).
- Provide the required density testing frequency and spatial distribution from the geotechnical plan (e.g., 1 test per 1,000 sq ft or per lift).
- Specify any proof‑rolling or proof‑loading procedures required before concrete or foundation placement as noted in the structural or geotechnical report.
- Confirm whether import fill must meet a laboratory gradation or contamination standard (e.g., no organics, <2% passing #200) and provide test spec.
- Provide acceptance criteria that will confirm the pad is ready for foundation placement (elevation tolerance, compaction tests, number of passing in‑situ density tests and proof‑roll sign‑off).
Temporary Dewatering and Groundwater Control
- Describe the anticipated groundwater conditions from borings or seasonal high groundwater elevation and reference the boring logs.
- Specify the temporary dewatering method you prefer or that the geotechnical report recommends (wellpoints, deep wells, sump pumping).
- Indicate whether a discharge permit or NPDES authorization will be required for dewatering and whether a plan exists.
- List expected contaminant testing or monitoring required for pumped discharge (pH, turbidity, TSS, contaminants of concern per environmental report).
- Specify standby power and contingency dewatering capacity required for rainy season or power failures as shown in the construction schedule.
- Confirm dewatering discharge location options shown on the SWPPP or site plan (to storm system, infiltration area, municipal sewer) and any agency approvals needed.
Underground Utility Trenching and Installation
- Provide utility as‑built drawings, existing service map, or GIS layers showing existing mains and laterals on or adjacent to the parcel.
- Specify trench depth, bedding and backfill materials per utility standard details for water, sanitary, storm, and telecom shown on civil details.
- Indicate required pressure and leak testing procedures for potable water mains and expected test documentation.
- List conduit sizes, fiber/telecom pull‑string requirements, and manhole spacing from the communications plan or utility scope.
- Specify the required backfill compaction standard around utilities and typical density testing frequency called out in the civil details.
- Indicate whether CCTV inspection, mandrel tests, or camera documentation are required for sanitary/storm piping acceptance and how many linear feet per run.
Perform Municipal Utility Tie‑ins
- Provide the municipality/utility district tie‑in requirements or reference the utility permit drawings and connection points.
- Specify required municipal inspections or witness points for tie‑in (meter set, pressure test, chlorination, backflow preventer) and expected sign‑offs.
- Indicate expected municipal scheduling constraints for service activation (lead time for meter, transformer, or sewer connection).
- Specify required documentation for acceptance of the tie‑in (municipal sign‑off form, as‑built drawings, pressure test logs).
- Confirm responsible party for securing municipal permits and coordinating inspections (you, contractor, or shared responsibility).
- Provide the evidence that will validate municipal tie‑in completion (signed municipal inspection, meter set photo, meter/energization certificate).
Stormwater Infrastructure Construction (BMPs, Basins, Pipes)
- Provide the stormwater design criteria or drainage report reference (design storm, discharge rates, allowable release rates).
- Specify the types of BMPs and basins required (detention pond, retention basin, bioretention, infiltration trench) as shown on the civil drawings.
- Indicate the required materials and pipe classes for storm sewer runs and the typical manhole/structure details from the civil standard details.
- Specify required hydraulic performance verification or post‑construction testing (as‑built survey to confirm basin volumes, infiltration testing).
- Confirm maintenance access and required protective measures during construction (siltation forebays, sediment traps, construction access ramps).
- Provide the acceptance evidence for stormwater infrastructure performance (as‑built elevations, hydraulic comparison to design, post‑construction inspection report).
Erosion Control and Sediment Management Installation
- Provide the draft SWPPP, erosion control plan sheets, or the permit references that govern silt fence, inlet protection, and turbidity controls.
- Specify required materials and installation standards for erosion controls (silt fence type, wattles, sediment basins) from local code or the SWPPP.
- Indicate required inspection frequency and reporting for erosion controls during rainy season as required by NPDES or local ordinance.
- List temporary stabilization measures expected after clearing and before final stabilization (temporary seeding, tackifier, erosion mat).
- Specify who will maintain erosion control measures during construction and how change‑orders for failures should be handled.
- Indicate any turbidity or discharge monitoring limits called out by the permit that will require field testing and logs.
Wetland Mitigation and Habitat Restoration Works
- Provide the jurisdictional delineation report and any mitigation ratios or mitigation plan references required by regulatory agency permits.
- Specify the mitigation approach expected (offsite mitigation bank credits, on‑site mitigation area, in‑lieu fee) and reference the mitigation banking instrument if used.
- Indicate the performance standards for restored habitat (survival rates, species list, monitoring years) as called out in the permit conditions.
- List seasonal planting windows or protection periods for restoration work that are in the mitigation plan or environmental permit.
- Specify long‑term monitoring and maintenance obligations required after construction (monitoring reports, replacements per year).
- Indicate who will secure mitigation credit purchases or complete permit required restoration (you, contractor, or third‑party mitigation provider).
-
Commercial & Commitment
Finalize commercial terms, payment milestones, risk allocation, mobilization triggers, and any prerequisite investigations or permits.
Agreement Modules
- Master Services Agreement (MSA)
- Statement of Work (SOW)
- Payment & Milestone Schedule
- Mobilization Trigger Agreement
- Conditions Precedent: Permits & Investigations
- Authorization for Site Access & Geotechnical Investigations
- Risk Allocation & Contingency Agreement
- Change Order Agreement
- Performance Security & Warranty
- Insurance & Indemnity Schedule
- Acceptance Certificate & Final Billing
-
Construction
Lock operational readiness, sequence site execution, and validate milestones through mobilization to acceptance.
-
Pre-Construction Readiness
Capture concrete readiness facts required to mobilize — geotechnical deliverables, survey baselines, permits status, utility availability, site access, and named owners.
Pre-Deployment Questions
Environment and site access
- Site identifier(s) for this readiness check (parcel number or short site name). If multiple sites, list each separately so we can plan per site.
- Legal and physical site access status (so we can schedule haul routes and mobilization).
- Known site access constraints or blackout windows (road weight limits, tenant operations, seasonal closures). Provide dates or brief description.
Geotechnical and survey deliverables
- Final geotechnical report and recommended design parameters delivered? (If not, provide expected delivery date.)
- Survey baseline and control status (horizontal/vertical control, topo, and boundary resolution) required to set pad elevations.
- If subsurface testing shows rock, high groundwater, or unsuitable soils beyond typical expectations, is there an accepted contingency approach or allowance?
Permits, utilities, and site readiness
- Which core permits are approved for mobilization? (Select all approved; list remaining permits and dates in the follow‑up field.)
- If any permits are not approved, list each permit and the expected approval date or gating action (one line per permit). This feeds the critical‑path schedule.
- Which utilities are available at the site boundary without extension work? (Select all that apply.)
- If any utility requires third‑party coordination or municipal approvals, provide the owning agency or utility company and the anticipated availability window in the DeploymentConfig (name here so we can assign follow up).
People, owners, and mobilization timing
- Named owners: provide one point of contact (name and role) for each workstream — geotech, survey, permitting, utilities coordination, and site logistics. (Used for approvals and daily coordination.)
- Target mobilization date when crews must be onsite to meet your schedule, or the earliest/latest acceptable mobilization window if flexible.
-
Construction Schedule & Execution
Plan and execute clearing, mass earthwork, utility rough-in, stormwater infrastructure, and roadwork with integrated scheduling, owners, and inspection coordination.
-
Site Acceptance Checklist
Verify pad elevations, compaction and testing, stormwater function, utility tie-ins, permit inspections, and punch-list closure before final acceptance and billing.
Checklist items
- Receive certified final grade survey report
- Receive geotechnical compaction and test results
- Obtain stormwater as-built drawings and performance inspection
- Obtain written Permission to Operate (PTO) or meter activation for each utility
- Complete electrical energization LOTO verification
- Receive final permit closeout or inspection certificates
- Close all punch-list items with buyer sign-off
- Deliver final as-built drawings, equipment lists, and O&M manuals
- Confirm site turnover of access, permanent safety controls, and signage
- Obtain final acceptance certificate and trigger final invoice
-
-
Success
Confirm delivery against success signals, manage warranty and punch-list items, and maintain a shared channel for issues and continuous improvement.
Success Reviews
- Closeout Health Check (weeks 1-4)
- First Measurement Review (weeks 4-10)
- 90-Day Warranty & Performance Review (around day 90)
- Quarterly Continuous Improvement Review
Issues & Enhancements
- Compile a backlog closure plan for long-tail warranty items with target dates and monitoring steps.
- Confirm whether warranty defect rate and punch-list closure time meet the thresholds recorded in the Site Acceptance Checklist or require extended remediation.
- Agree on any extended remediation plan or monitoring approach with milestone dates.
- Set the recurring reporting cadence for warranty performance and unresolved items.
- Document the extended remediation plan with milestones and deliver it to the shared channel.
- Establish the recurring warranty performance report format and schedule.
- Open escalation tickets for any high-severity items that exceed target resolution windows.
- Trend review of core metrics
- Reduce recurring defect categories by agreeing concrete process or checklist changes.
- Improve average punch-list closure time and first-pass compaction test pass rate toward the targets recorded in the Site Acceptance Checklist.
- Close or transition long-tail warranty items with clear timelines or monitoring plans.
- Publish a lessons-learned summary that lists recurring root causes and the agreed process changes.
- Update the pre-construction and QA checklists to reflect agreed changes and circulate the revised templates.
- Reconfirm acceptance criteria and documentation
- Confirm that all required as-built documentation referenced in the Site Acceptance Checklist has been delivered or has an agreed delivery date.
- Produce a prioritized initial punch-list with remediation deadlines and an established shared issue channel.
- Agree the cadence for short-term punch-list burn-down updates until the first measurement review.
- Publish the complete as-built package and test reports to the shared project channel.
- Create and circulate the initial punch-list with remediation target dates and severity classification.
- Activate the warranty/issue tracking channel and post the escalation procedure.
- Present current metric state
- Establish whether the open punch-list count and compaction test pass rate meet or are trending to the Site Acceptance Checklist targets.
- Agree a timebound remediation plan for any off-target metrics with concrete milestones and retest dates.
- Ensure the warranty register is updated to reflect all corrective actions and retest requirements.
- Log all corrective actions and retest requirements into the warranty register with target completion dates.
- Schedule required rework and verification tests and circulate the timeline to the shared channel.
- Produce a short report summarizing root-cause findings for any metric gaps identified in this meeting.
- Cumulative performance summary
- Verify as-built deliverables
- Severity triage and remediation status
- Recurring root-cause analysis
- Diagnose root causes for gaps
- Process and checklist updates
- Agree corrective actions and timelines
- Surface early punch-list and warranty items
- Decide on extended remediation or monitoring needs
- Update warranty and punch-list register
- Finalize escalation and long-term communication cadence
- Backlog and long-tail item review
- Immediate remediation and short-term schedule
- Confirm communication and issue channel