Professional Services › Architecture & Engineering Firms › Mechanical, Electrical & Plumbing

Building Performance Testing

Project-based professional services where design authority, owner approval, and multi-discipline coordination determine delivery.

Example organizations in this space: Intertek DEKRA Bureau Veritas ETC

This interactive experience is the shipped product itself — the same application code customers run in production, mounted read-only in your browser over a real sample journey. Not a video, not a mockup: because the demo and the product are one codebase, it can never drift from the real thing.

Inside this journey
  1. Project & Site Discovery

    Map project drivers (LEED/code/comfort), stakeholders, occupancy timeline, and known system performance issues to establish success criteria.

    Discovery Questions

    Quick project snapshot

    • How would you summarize this project's purpose and the primary performance requirement, for example LEED enhanced commissioning, a local code mandate, tenant comfort, or energy reduction?
    • Which of these best describes the project's current phase? Options: Design and review, Pre-construction / procurement, Construction, major systems being installed, Systems installed, commissioning imminent, Occupied with known comfort or energy issues
    • Who on your team is the day-to-day owner for commissioning coordination and long-term operations? Options: Director of Facilities / FM, Owner's project manager, Capital projects director, Sustainability program manager, Third-party owner's rep, Other — please specify
    • When is the owner targeting substantial completion or first occupancy? Options: Within 4 weeks, 4 to 12 weeks, 3 to 6 months, 6+ months, No firm date yet
    • Tell me about any tenant or past building performance problems that are shaping how you want this building to perform now.

    Where buildings usually fail the owner, fast

    • If this project opens with the same hot-and-cold complaints as your last building, what immediate operational and financial consequences do you expect for your team?
    • Which systems do you expect will be most at risk during turnover? Options: HVAC distribution (ducts, fans), VAV boxes and controls, Chiller/boiler plant, Domestic hot water, Electrical distribution, Building envelope (air/thermal leaks), Plumbing fixtures, Other
    • How many previous projects in your portfolio have delivered late because of unresolved commissioning items? Options: 0, 1 to 2, 3 to 5, 6 or more
    • Describe the last time you had to escalate a system-performance dispute with a contractor, and what ultimately resolved it.
    • What single unresolved deficiency would force you to delay acceptance?

    The hidden costs that usually show up later

    • What operational cost or tenant claim keeps you awake when you think about handover risks?
    • Who else inside your organization shares that same urgency or would be most affected by a failed handover? Options: Operations / FM, Capital projects, Procurement, Sustainability, Legal / Risk, Executive leadership, Other
    • Do you have a formal target for first-year energy reduction or comfort-complaint reduction after commissioning? Options: Energy reduction target exists, Comfort complaint reduction target exists, Both targets exist, No formal target
    • On average, after defects are discovered, how long until tenant complaints escalate to formal claims or executive attention? Options: Less than 1 month, 1 to 3 months, 3 to 6 months, More than 6 months
    • Pick the single metric you would use to judge commissioning success, time to resolve, number of comfort complaints, or energy overrun. Options: Time to resolve defects, Number of comfort complaints, Energy use versus baseline, First-year warranty claims, Other

    What typically blocks testing on site

    • Point to the team or contractor that has slowed testing on past projects, and tell me why that happened.
    • Do you have access, phasing, or blackout windows that will prevent testing during certain months? Options: Yes, strict blackout windows, Limited access but workable, No major constraints known, Unsure / need to confirm
    • When mechanical systems must be taken offline for trade work, what typically breaks the planned test sequence?
    • List the specific subcontractors or trade partners whose cooperation is required to run full sequences of functional tests.
    • Give an example of a contractor response to a punch list that suggested deficiencies would not be resolved promptly.
    • If the general contractor declines to allow witness testing within your critical access window, will you still accept the current handover date? Options: Yes, No, Only with a written remediation plan and penalties, Unsure

    Competitive landscape and other options you might choose

    • Name the types of solutions currently on the table, for example incumbent firm, internal staff execution, contractor-led testing, or another independent firm, and tell me what would make you stick with them.
    • Select all the options you have formally evaluated so far Options: Incumbent commissioning firm, Other independent commissioning firms, In-house commissioning by FM team, Contractor-led testing, Controls vendor-only tuning, No formal commissioning option evaluated
    • Under what conditions would you keep your current approach instead of hiring an outside partner?
    • Has anyone on your team proposed handling commissioning internally rather than using an external firm? Options: Yes, No
    • Would an incumbent offer that included seasonal verification and named witnesses remove the need for a third-party commissioning engagement? Options: Yes, Maybe, depending on scope, No, Unsure

    Practical readiness and technical constraints

    • Identify the single integration, permit, or access barrier that would halt testing on day one.
    • Confirm whether your controls network allows remote read and write access for third-party testing and data collection. Options: Yes, with credentials and API access, Yes, but only with onsite access, No remote access available, We do not know yet
    • Please list the team or role that owns the building automation system accounts and who can provide credentials or API access.
    • Are there permits, site safety orientations, or insurance certificates required before our field team can perform work? Options: Site safety orientation, Vendor insurance certificate, Confined space training, Lockout/tagout, Hot work permit, No special requirements known
    • Is there any contractual restriction, warranty condition, or pending certification that would prohibit third-party testing within the next 90 days? Options: Yes, No, Unsure

    Acceptance criteria that control the outcome

    • Point to the acceptance criterion that would make you withhold final payment or occupancy.
    • List the specific test results, report elements, or defect-closure evidence that must appear in the final commissioning report for you to accept handover.
    • Enter the number of named stakeholders who must sign off on functional test reports before occupancy Options: 1, 2, 3 to 5, 6 or more
    • Identify the role accountable for closing defects after commissioning and during the 12-month seasonal verification period Options: General contractor, MEP subcontractor, Owner's facilities team, Owner's project manager, Third-party commissioning agent, Other
    • Would you be prepared to delay final acceptance if seasonal verification at month nine uncovers unresolved deficiencies? Options: Yes, No, Depends on severity, Unsure

    Agreeing next steps without surprises

    • Name the deadline that would make you abandon the search for a new commissioning partner and keep the current approach.
    • Select the contract terms that are non-negotiable for you Options: Liability cap and insurance minimums, Named deliverables and test protocols, Seasonal verification included, Access to controls data and APIs, Schedule guarantees or liquidated damages, Warranty for testing results
    • Tell me your ideal start date for field commissioning and any blackout dates we should avoid.
    • Choose the billing structure you prefer Options: Lump sum proposal, Time and materials with a not-to-exceed cap, Milestone-based payments tied to deliverables, Other
    • Assuming blackout dates, confirmed controls access, and a scheduled two-week witness window are met, would you be ready to move to mutual commit within 14 days? Options: Yes, Maybe, No
  2. Commissioning Approach Review

    Walk through the commissioning strategy, sequencing with construction, and how functional tests and reporting will protect the owner's acceptance timeline.

    Solution Experience

    • Commissioning Approach Review
    • Confirm the current state and its cost
    • Provide the project construction milestone schedule, including the target occupancy date and major system installation dates.
    • You confirm that the proposed sequencing eliminates the identified risks to your acceptance timeline.
    • Deliver a sequenced functional-test plan mapped to the provided milestones within 5 business days after this session.
    • You confirm that the reporting and defect disposition workflow provides clear owners and timing to close deficiencies before turnover.
    • Map the commissioning sequence to your construction milestones
    • Demonstrate the test and reporting workflow that closes deficiencies
    • Schedule a site-readiness checkpoint for the week before pre-functional testing begins.
    • You agree on the remaining evidence and decision points required before a contracting decision.
    • Confirm the acceptance sign-off owners and the criteria they will use to accept or reject closed defects.
    • Validate alignment and decision points
    • Forced validation, confirm this maps to your needs
    • Commissioning Approach Review
    • Commissioning Approach Deck
    • Commissioning Approach Brief
    • meeting
    • slides
    • document
  3. Commissioning Scope

    Define systems in scope, phased testing windows, deliverables (plans, functional tests, reports), responsibilities, and seasonal verification requirements.

    1. Commissioning Scope

      Define systems in scope, phased testing windows, deliverables (plans, functional tests, reports), responsibilities, and seasonal verification requirements.

      Scope Configuration

      • Pre-Functional Checklist Execution
      • HVAC Functional Performance Testing
      • Controls Sequence and Point-to-Point Testing
      • Air and Water Balancing
      • Envelope Integrity Testing (blower door, thermal imaging)
      • Electrical Systems Functional Testing
      • Plumbing Functional Testing and Leak Verification
      • Emergency Power and Life-Safety Systems Testing
      • Deficiency Documentation with Corrective Actions
      • Punchlist Resolution Support at Substantial Completion
      • Systems O&M Manual Development
      • Post-Occupancy Verification and Seasonal Re-Testing (12 months)
      • Facilities Team Controls and Maintenance Training
    2. Scope Questions

      Scope Questions

      Pre-Functional Checklist Execution

      • Which systems will you require pre-functional checklists for (refer to the commissioning plan or design drawings)? Options: HVAC air handlers (AHU/RTU), VAV/terminal units, Chilled water plant, Hot water plant, Controls/points, Electrical distribution, Plumbing risers, Building envelope
      • How many staged pre-functional walkthroughs per typical occupied zone do you expect before functional testing (for example: terminal device stat, ductwork inspection, control point verification)? Options: One, Two, Three or more
      • Who will provide as-built mechanical drawings, updated control point list (CPL), and submittal-responses used to build the pre-functional checklists? Options: General contractor, Mechanical subcontractor, Controls contractor, Design team/engineer, We will provide missing items
      • When do you plan to complete pre-functional checklists relative to the start of functional tests (for example: 2 weeks before, 1 week before, same day)? Options: 2+ weeks before scheduled functional tests, 1 week before, Concurrent with functional test start, Not defined yet
      • List any site access, safety, or lockout/tagout (LOTO) restrictions that will affect checklist execution (for example: occupied floors, live electrical rooms, constrained rooftop access).
      • Confirm whether you require digital checklist forms with photo attachments and timestamped GPS or zone labels tied to each checklist item for traceability. Options: Yes, No

      HVAC Functional Performance Testing

      • Select HVAC systems that must be covered by functional performance tests per the design intent and commissioning plan (examples: AHU, RTU, VAV, heat pump, chilled beams). Options: Air handling units (AHUs), Rooftop units (RTUs), Variable air volume (VAV) boxes, Heat pumps/VRF, Chilled beams, Dedicated outdoor air systems (DOAS)
      • Estimate the number of representative sequences of operation to be tested per major air handling unit (for example: economizer modulation, heating/cooling changeover, frost control). Options: 1–2 sequences, 3–5 sequences, More than 5 sequences
      • Identify who will coordinate scheduling of HVAC functional test windows with the mechanical subcontractor and site superintendent. Options: General contractor coordinator, Mechanical subcontractor lead, Owner's project manager, We will coordinate
      • Provide the date or milestone when condenser/chilled-water and hot-water systems will be available for full-load HVAC performance tests.
      • Provide target acceptance thresholds for HVAC tests drawn from the design basis (for example: supply temperature tolerance ±2°F, airflow variance ±10% of design cfm).
      • Specify any LEED enhanced commissioning or local energy-code HVAC test requirements that expand the scope (for example: additional sequences or commissioning agent witnessing). Options: LEED enhanced commissioning applies, Local code third-party commissioning applies, Owner-specified additional tests, None of the above

      Controls Sequence and Point-to-Point Testing

      • Choose the control sequences from the sequence of operations that must be validated with point-to-point checks (for example: economizer control, condenser staging, chilled-water reset). Options: Economizer and OA control, Heating and cooling staging, Supply air temperature reset, Demand-controlled ventilation, Plant sequencing
      • Report the current count of control points on the control point list (CPL) to size point-to-point testing effort. Options: Less than 200 points, 200–1,000 points, More than 1,000 points, Unknown
      • Assign who will provide BAS access credentials, a list of IP addresses, and any remote VPN or commissioning tool access required for point-to-point verification. Options: Controls contractor, IT/network team, General contractor, We will provide
      • Schedule when point-to-point checkout should occur relative to mechanical functional tests and TAB (for example: after pre-functional checklists and preliminary TAB, before final functional test). Options: After pre-functional checklists, After preliminary TAB, Concurrent with functional tests, Not defined
      • Select the controls testing deliverables you require: annotated CPL, point-to-point field verification log, sequence test scripts, BAS screenshot captures, and trend data exports. Options: Annotated CPL, Field verification log, Sequence test scripts, BAS screenshots, Trend captures (CSV)
      • Indicate whether trending will be enabled for at least 72 hours prior to sequence testing to capture baseline behavior. Options: Yes, No

      Air and Water Balancing

      • Pick balance deliverables required from the TAB contractor: certified TAB report, instrument calibration certificates, and as-left airflow and hydronic reports. Options: Certified TAB report, Instrument calibration certificates, As-left airflow reports, Hydronic flow/valve authority report
      • State how many zones or terminal devices require full certified air balancing versus sample spot checks (provide count or percentage). Options: All terminal devices, Representative sample (25%), Representative sample (50%), Custom - specify in free text
      • Provide who will grant access to central plant equipment and chiller controls for pump speed and valve authority adjustments during TAB. Options: Plant operator, Mechanical subcontractor, General contractor, We will provide access
      • Schedule when the preliminary TAB report will be available for review relative to functional testing (for example: at least 7 days before HVAC FPT). Options: 7+ days before FPT, 3–6 days before FPT, Concurrent with FPT, Not defined
      • Set acceptance tolerances for room airflow and terminal device flows based on design documents (for example: ±10% of design cfm, face velocity limits).
      • Flag any TAB scheduling constraints such as seasonal water temperatures, chiller sequencing, or occupied-hours restrictions that will affect balancing.

      Envelope Integrity Testing (blower door, thermal imaging)

      • Choose which envelope tests are required for your project: blower door for airtightness, thermal imaging of façades, or infrared during pressure differentials. Options: Blower door (ACH50), Thermal imaging of façades, Infrared during pressure differential, Air leakage per façade section
      • Indicate how many façades or representative units must be tested to satisfy energy code, LEED, or owner's requirements. Options: Whole-building sampling per code, At least one representative façade per orientation, Per-unit testing for multi-family, Custom - specify
      • Name who will provide exterior access (scaffolding, lifts) and safe work plans for thermal imaging and blower door setup. Options: GC to provide access, Trade subcontractor, Owner arranges access, We will arrange
      • State the envelope testing window relative to exterior finishing and glazing installation (for example: after glazing and sealants, before final cladding). Options: After glazing/sealants installed, After exterior cladding complete, During final punchlist window, Not defined
      • Provide the required leakage threshold used for acceptance (for example: target ACH50 or maximum cfm/ft2).
      • Confirm whether you require thermographic reports with annotated images and location tags for every identified thermal anomaly. Options: Yes, No

      Electrical Systems Functional Testing

      • Select electrical systems to include in functional testing: main distribution, panelboards, lighting control, automatic transfer switches (ATS), generator, and UPS integration. Options: Main distribution/MCC, Panelboards, Lighting controls, Automatic transfer switches (ATS), Generator/UPS
      • Specify how many ATS or generator full-load tests are required by specification (for example: one full-load run, two-run schedule). Options: One full-load run, Two full-load runs, Run per spec/custom
      • Assign who will coordinate utility shutdowns, temporary power, and notification to tenants or critical operations for electrical testing. Options: Utility coordinator, General contractor, Owner's facility lead, We will coordinate
      • Deliver the date that single-line diagrams (SLD) and as-built electrical drawings will be available for test planning.
      • Set acceptance criteria for voltage, frequency, and protective device operation during load testing (for example: ±5% voltage under rated load, transfer within specified ms).
      • List any sensitive equipment or systems that require staged outages, vendor witness, or special limitations during electrical testing (for example: data center racks, medical imaging).

      Plumbing Functional Testing and Leak Verification

      • Select plumbing subsystems requiring functional testing: domestic hot water, chilled/hydronic piping, sanitary risers, storm drains, and specialty systems. Options: Domestic hot water, Hydronic/chilled water piping, Sanitary risers, Storm drainage, Grease interceptors
      • State the number of fixture groups or risers that must be pressure-tested and inspected for leaks. Options: All risers/fixture groups, Representative sampling, By riser type (specify)
      • Provide who will perform flushing, sterilization, or bacteriological testing if required for domestic water systems prior to commissioning. Options: Plumbing subcontractor, Third-party water treatment, We will coordinate
      • Schedule when hydrostatic or pneumatic tests should be executed relative to drywall, finishes, and ceiling closures. Options: Before drywall/finishes, After drywall but before ceilings, After ceilings installed, As-directed by GC
      • Set acceptance thresholds for flow rates and pressure drops on critical mains and fixture groups (for example: ±10% of design flow).
      • Confirm whether you require CCTV sewer line inspection reports and video logs for sanitary/storm piping verification. Options: Yes, No

      Emergency Power and Life-Safety Systems Testing

      • Choose life-safety systems that must be tested: emergency lighting, fire alarm interlocks with HVAC, sprinkler flow switches, stair pressurization, and smoke control. Options: Emergency lighting, Fire alarm-HVAC interlocks, Sprinkler flow switches, Stair pressurization, Smoke control systems
      • Specify required generator run conditions: number of full-load runs, duration per run, and required recovery time. Options: One run per spec, Two runs per spec, Custom duration (specify)
      • Provide the authority having jurisdiction (AHJ) or fire marshal contact who must witness or approve life-safety system tests.
      • Schedule when fire alarm integration checks should be performed relative to panel energization and fire alarm vendor commissioning. Options: After panel energization, During final commissioning, As scheduled with fire alarm vendor
      • Set required acceptance actions and retest protocol if a life-safety interface fails during testing (for example: immediate stop, corrective action timeline).
      • List any third-party witnesses, vendor representatives, or AHJ presence required for specific life-safety or emergency power tests.

      Deficiency Documentation with Corrective Actions

      • What format do you require for deficiency reports and corrective actions: annotated functional test logs, photo evidence, contractor corrective action plans, or shared ticket entries? Options: Annotated functional test logs, Photo evidence linked to location, Contractor corrective action plan, Shared ticket in CMMS
      • Assign who will own tracking and closure of deficiency items in the shared ticketing channel and provide role titles (for example: facilities lead, commissioning agent, GC superintendent).
      • Provide the prioritization criteria to be applied to deficiencies (for example: safety/critical, impacts acceptance, cosmetic) used to sequence corrective work. Options: Safety/Critical first, Affecting owner acceptance next, Cosmetic/low priority last
      • Schedule when re-testing should occur after corrective action completion and what minimum evidence must be submitted for re-test acceptance (for example: data logs, photos, retest report).
      • What acceptance criteria will confirm a documented deficiency is resolved (for example: re-test metrics within design tolerance, contractor-signed completion certificate, or owner verification)? Options: Re-test metrics within design tolerance, Contractor sign-off with supporting evidence, Owner/facility verification and sign-off
      • Outline escalation steps and timelines if a deficiency cannot be resolved before substantial completion (for example: conditional acceptance, warranty holdback, extended testing window).

      Punchlist Resolution Support at Substantial Completion

      • Choose the punchlist workflow you prefer: live shared ticketing with status updates, periodic consolidated punchlist reports, or daily field updates with photographic evidence. Options: Live shared ticketing (recommended), Periodic consolidated reports, Daily field update emails
      • List how many named contacts from your facilities and project teams will be authorized to approve punchlist closures (provide names or role counts). Options: 1–2 approvers, 3–5 approvers, More than 5 approvers
      • Assign who will coordinate contractor mobilization and access for punchlist corrections during the substantial completion window. Options: General contractor, Trade subcontractor, Owner's PM, We will coordinate
      • Provide the scheduled date for the final punchlist turnover meeting relative to the certificate of occupancy milestone.
      • What evidence will validate punchlist closure for owner acceptance (for example: signed-off functional test reports, corrected TAB values, or photographic verification)? Options: Signed-off functional test reports, Corrected TAB values with retest data, Photographic and ticket evidence
      • State any fixed-fee boundaries or explicit out-of-scope items for punchlist support (for example: major system retrofits, tenant-provided equipment, or warranty implementation tasks).
  4. Mutual Commit

    Finalize commercial and contractual terms, acceptance criteria, dependencies, and the governance needed to execute testing without delaying handover.

    Agreement Modules

    • Master Services Agreement (MSA)
    • Statement of Work (SOW)
    • Fee Schedule & Payment Terms
    • Acceptance Criteria & Test Governance Agreement
    • Site Access & Coordination Addendum
    • Change Order Agreement
    • Insurance & Indemnity Certificate
    • Post-Occupancy Verification Addendum
    • Acceptance Sign-Off & Handover Checklist
    • Data Processing & Confidentiality Addendum (conditional)
  5. Deployment

    Coordinate site readiness, execute field testing without delaying completion, and capture test records for transparent deficiency resolution.

    1. Site Coordination & Readiness

      Confirm access windows, construction sequencing, equipment availability, witness requirements, and named points of contact before fieldwork begins.

      Pre-Deployment Questions

      Environment and site access

      • Which building systems will the seller need physical field access to at the start of deployment? (select all that apply — this tells us which trades and areas to coordinate) Options: HVAC (ducting, AHUs, RTUs), Electrical (switchgear, panels), Plumbing (pumps, domestic hot water), Controls / building automation, Envelope (windows, roof, doors), Fire protection / life safety, Vertical transport (elevators/escalators), Other
      • Is this deployment for a single site or multiple sites? (If multiple, we'll request site‑level readiness for each.) Options: Single site, Multiple sites
      • Primary site for initial fieldwork (site name and primary area/entrance/floor) — so we know where to stage crews and equipment.

      Equipment and materials

      • Are all long‑lead or test‑critical equipment items required for initial functional tests delivered and staged on site? Options: Yes — all critical items on site, Partial — some items on site, some outstanding, No — critical items arriving during testing, Unsure — need confirmation
      • If any critical equipment is outstanding, list the system, item, and expected arrival week (or write 'none') — this lets us sequence tests without delays.
      • Are spare parts, temporary meters, and required access tools provided by the buyer on site or will the seller bring them? Options: Buyer provides on site, Seller will bring all required spares and meters, Hybrid — buyer provides some, seller brings remainder, TBD

      People and ownership

      • Provide the named points of contact for field coordination (name, role, best contact method, regular hours) — these people will receive schedule invitations and run sheets.
      • Which on‑site roles must be present to witness tests or provide trade support? (select all that apply) Options: General contractor superintendent, Owner's representative / facilities manager, HVAC / mechanical foreperson, Electrical foreperson, Controls contractor technician, Plumbing foreperson, Third‑party vendor representative, Other
      • Are there pre‑qualification or credentialing requirements for seller personnel (safety orientation, badging, background check, insurance certificates)? If yes, indicate which and who issues approval. Options: No, Safety orientation required, Badging / site ID required, Background check / pre‑qualification required, Insurance / certificate submission required, Other

      Timing and constraints

      • Confirm regular site working hours and earliest/latest permissible start times for fieldwork (e.g., M–F 7:00–17:00). If different by area, note differences — so we can schedule visits within allowed windows.
      • List any blackout dates or restricted windows (tenant move‑in, public events, major inspections) when fieldwork cannot occur.
      • What is the critical acceptance milestone date the deployment must not delay (certificate of occupancy, tenant move‑in, or owner's final acceptance)? If unknown, write 'TBD' — we will treat this as the hard constraint for scheduling.
    2. Onsite Testing & Commissioning

      Execute pre-functional checks, air/water balancing, functional performance tests, and envelope diagnostics with clear owners and a scheduled test plan.

    3. Test Witness & Meeting Records

      Document witness sessions, meeting minutes, photographic evidence, and defect dispositions to ensure transparent corrective-action tracking.

      Meeting Notes

      • Witness Planning and Evidence Protocol
      • Onsite Witness Session Template
      • Defect Triage and Disposition
      • Meeting Records Finalization and Handover Package
      • Flag any immediate defects in the shared defect tracker with provisional severity and a short description
      • Schedule re-test or follow-up witness session for any tests placed on hold
      • Review compiled meeting minutes and witness records
      • Reconcile defects from recent witness records
      • Final evidence package approved and ready to be linked to the project handover deliverables.
      • Any missing evidence items identified with deadlines for completion or replacement.
      • Recurring follow-up cadence and escalation path set for unresolved defects.
      • Upload the approved evidence package to the platform and link it to the project handover folder
      • Publish the finalized meeting minutes and a summary of open items to the shared workspace
      • Set recurring check-ins and escalation steps for unresolved items until closed
      • List required evidence items for defects needing more data and request them within the agreed deadline
      • Publish the defect disposition log with assigned remediation actions and target dates
      • Items needing more data have a documented evidence list and a deadline for submission.
      • Confirm scope and success criteria
      • Finalized witness schedule with sequenced test windows and time buffers for re-runs.
      • Approved evidence checklist and photo/data naming convention to be used on every session.
      • Agreed storage location and access/retention rules for witness records on the platform.
      • Publish the finalized witness schedule to the shared workspace
      • Upload the evidence checklist and photo/data naming convention to the project folder
      • Confirm and publish the access list and retention policy for stored records
      • Open high severity defect tickets in the shared tracking channel and link evidence
      • Remediation target dates and re-witness windows are recorded for all remediate dispositions.
      • Each defect has a recorded disposition and a clear corrective action or required evidence request.
      • Pre-session readiness check
      • A completed witness session record that includes minutes, photo log, and raw test data saved to the project folder.
      • Any immediate defects or tests on hold recorded with provisional severity and clear next steps.
      • Confirmation that all evidence follows the agreed naming convention and metadata requirements.
      • Attach the witness session minutes, photo log, and raw test data to the session record in the platform
      • Run and observe the functional test
      • Agree witness schedule and sequencing
      • Verify photo and data completeness against the checklist
      • Examine photographic and measurement evidence per defect
      • Decide disposition and remediation plan
      • Define evidence standard and naming convention
      • Capture photographic and data evidence
      • Approve final evidence package and access rules
      • Confirm sign-off, storage, and access process
      • Document immediate defects and provisional holds
      • Set remediation timeline and re-witness windows
      • Confirm follow-up cadence for unresolved items
  6. Post-Occupancy Validation & Success

    Conduct seasonal verification, confirm deficiency resolution, and maintain a shared ticketing channel for warranty issues and continuous improvement.

    1. Post-Occupancy Validation & Success

      Conduct seasonal verification, confirm deficiency resolution, and maintain a shared ticketing channel for warranty issues and continuous improvement.

      Success Reviews

      • Post-Occupancy Health Check (weeks 1-4)
      • First Performance Measurement (weeks 4-10)
      • Acceptance Gate Review (around day 90)
      • 6-Month Seasonal Verification Check
      • Quarterly Operational Review (ongoing)
      • Update the continuous improvement backlog and circulate priorities for the next quarter.
      • Confirm next verification steps and the evidence required to close conditional items.
      • Publish the acceptance decision record and attach supporting test evidence.
      • Create remediation tasks for all failed or conditional criteria with target retest dates.
      • Schedule the verification retest window and reserve required access and equipment.
      • Present seasonal test outcomes
      • Confirm seasonal verification completion rate is tracking to Commissioning Scope expectations.
      • Identify and document any energy performance variances that require remediation.
      • Ensure warranty tickets are being resolved and recurring issues are captured for systemic fixes.
      • Log any seasonal remediation tasks with retest windows in the shared ticketing channel.
      • Produce a short summary of energy variance analysis and recommended adjustments.
      • Plan any additional envelope or HVAC diagnostics required for the next seasonal window.
      • Ticketing channel burn-down review
      • Keep warranty ticket backlog reducing in line with burn-down targets from Commissioning Scope.
      • Ensure comfort complaint rate is stable or improving and capture root causes for any increases.
      • Maintain a prioritized continuous improvement backlog for the next quarter.
      • Close or escalate tickets that are aged beyond the agreed SLA and document next steps.
      • Schedule any agreed short operational tasks with dates and required site access.
      • Reconfirm acceptance criteria and owners
      • Confirm pre-functional checklist completion rate and identify any critical items requiring immediate action.
      • Ensure the shared warranty/ticketing channel is operational and contains the initial defect list.
      • Agree remediation actions with clear timelines to avoid acceptance delays.
      • Publish the initial defect list and pre-functional checklist summary to the shared workspace.
      • Enable and verify access for buyer and seller teams to the warranty/ticketing channel.
      • Create remediation tasks for all critical open deficiencies with target close dates.
      • Present functional test results
      • Determine whether percent of functional tests passed is moving toward Commissioning Scope targets.
      • Agree remediation and retest timelines to improve median days to close deficiencies to target levels.
      • Capture any sequencing or access blockers and document mitigation steps.
      • Publish a prioritized retest schedule and required site access windows.
      • Log root-cause remediation tasks in the shared ticketing channel with resolution dates.
      • Update the functional test tracking spreadsheet with latest pass/fail status.
      • Restate numeric acceptance criteria
      • Produce a documented acceptance decision tied to the numeric targets in Commissioning Scope.
      • List any failed or conditional criteria with a clear remediation and retest timeline.
      • Comfort complaint and trend analysis
      • Review energy performance variance
      • Deficiency closure velocity
      • Present consolidated outcome data
      • Validate ticketing and communication channels
      • Review pre-functional checklist results
      • Document pass/fail per criterion
      • Root-cause diagnosis for gaps
      • Warranty ticket trends and dispositions
      • Continuous improvement backlog
      • Short operational actions
      • Adjust operational setpoints or sequences
      • Confirm retest and sequencing plan
      • Early operational observations
      • Formal acceptance decision
      • Agree immediate remediation actions
      • Agree remediation and verification timeline for failed items
    2. Tickets

      Tickets the customer raises land here once the journey is shared.

    3. Feedback

      Feedback from the customer lands here once the journey is shared.

First-Party AI ™

1-2 minutes please — Your AI agent is working

First-Party AI™ can make mistakes. Always check important information.