Building Performance Testing
Project-based professional services where design authority, owner approval, and multi-discipline coordination determine delivery.
This interactive experience is the shipped product itself — the same application code customers run in production, mounted read-only in your browser over a real sample journey. Not a video, not a mockup: because the demo and the product are one codebase, it can never drift from the real thing.
Inside this journey
-
Project & Site Discovery
Map project drivers (LEED/code/comfort), stakeholders, occupancy timeline, and known system performance issues to establish success criteria.
Discovery Questions
Quick project snapshot
- How would you summarize this project's purpose and the primary performance requirement, for example LEED enhanced commissioning, a local code mandate, tenant comfort, or energy reduction?
- Which of these best describes the project's current phase?
- Who on your team is the day-to-day owner for commissioning coordination and long-term operations?
- When is the owner targeting substantial completion or first occupancy?
- Tell me about any tenant or past building performance problems that are shaping how you want this building to perform now.
Where buildings usually fail the owner, fast
- If this project opens with the same hot-and-cold complaints as your last building, what immediate operational and financial consequences do you expect for your team?
- Which systems do you expect will be most at risk during turnover?
- How many previous projects in your portfolio have delivered late because of unresolved commissioning items?
- Describe the last time you had to escalate a system-performance dispute with a contractor, and what ultimately resolved it.
- What single unresolved deficiency would force you to delay acceptance?
The hidden costs that usually show up later
- What operational cost or tenant claim keeps you awake when you think about handover risks?
- Who else inside your organization shares that same urgency or would be most affected by a failed handover?
- Do you have a formal target for first-year energy reduction or comfort-complaint reduction after commissioning?
- On average, after defects are discovered, how long until tenant complaints escalate to formal claims or executive attention?
- Pick the single metric you would use to judge commissioning success, time to resolve, number of comfort complaints, or energy overrun.
What typically blocks testing on site
- Point to the team or contractor that has slowed testing on past projects, and tell me why that happened.
- Do you have access, phasing, or blackout windows that will prevent testing during certain months?
- When mechanical systems must be taken offline for trade work, what typically breaks the planned test sequence?
- List the specific subcontractors or trade partners whose cooperation is required to run full sequences of functional tests.
- Give an example of a contractor response to a punch list that suggested deficiencies would not be resolved promptly.
- If the general contractor declines to allow witness testing within your critical access window, will you still accept the current handover date?
Competitive landscape and other options you might choose
- Name the types of solutions currently on the table, for example incumbent firm, internal staff execution, contractor-led testing, or another independent firm, and tell me what would make you stick with them.
- Select all the options you have formally evaluated so far
- Under what conditions would you keep your current approach instead of hiring an outside partner?
- Has anyone on your team proposed handling commissioning internally rather than using an external firm?
- Would an incumbent offer that included seasonal verification and named witnesses remove the need for a third-party commissioning engagement?
Practical readiness and technical constraints
- Identify the single integration, permit, or access barrier that would halt testing on day one.
- Confirm whether your controls network allows remote read and write access for third-party testing and data collection.
- Please list the team or role that owns the building automation system accounts and who can provide credentials or API access.
- Are there permits, site safety orientations, or insurance certificates required before our field team can perform work?
- Is there any contractual restriction, warranty condition, or pending certification that would prohibit third-party testing within the next 90 days?
Acceptance criteria that control the outcome
- Point to the acceptance criterion that would make you withhold final payment or occupancy.
- List the specific test results, report elements, or defect-closure evidence that must appear in the final commissioning report for you to accept handover.
- Enter the number of named stakeholders who must sign off on functional test reports before occupancy
- Identify the role accountable for closing defects after commissioning and during the 12-month seasonal verification period
- Would you be prepared to delay final acceptance if seasonal verification at month nine uncovers unresolved deficiencies?
Agreeing next steps without surprises
- Name the deadline that would make you abandon the search for a new commissioning partner and keep the current approach.
- Select the contract terms that are non-negotiable for you
- Tell me your ideal start date for field commissioning and any blackout dates we should avoid.
- Choose the billing structure you prefer
- Assuming blackout dates, confirmed controls access, and a scheduled two-week witness window are met, would you be ready to move to mutual commit within 14 days?
-
Commissioning Approach Review
Walk through the commissioning strategy, sequencing with construction, and how functional tests and reporting will protect the owner's acceptance timeline.
Solution Experience
- Commissioning Approach Review
- Confirm the current state and its cost
- You confirm that the proposed sequencing eliminates the identified risks to your acceptance timeline.
- Provide the project construction milestone schedule, including the target occupancy date and major system installation dates.
- You confirm that the reporting and defect disposition workflow provides clear owners and timing to close deficiencies before turnover.
- Map the commissioning sequence to your construction milestones
- Deliver a sequenced functional-test plan mapped to the provided milestones within 5 business days after this session.
- You agree on the remaining evidence and decision points required before a contracting decision.
- Demonstrate the test and reporting workflow that closes deficiencies
- Schedule a site-readiness checkpoint for the week before pre-functional testing begins.
- Validate alignment and decision points
- Confirm the acceptance sign-off owners and the criteria they will use to accept or reject closed defects.
- Forced validation, confirm this maps to your needs
- Commissioning Approach Review
- Commissioning Approach Deck
- Commissioning Approach Brief
- meeting
- slides
- document
-
Commissioning Scope
Define systems in scope, phased testing windows, deliverables (plans, functional tests, reports), responsibilities, and seasonal verification requirements.
Scope Configuration
- Pre-Functional Checklist Execution
- HVAC Functional Performance Testing
- Controls Sequence and Point-to-Point Testing
- Air and Water Balancing
- Envelope Integrity Testing (blower door, thermal imaging)
- Electrical Systems Functional Testing
- Plumbing Functional Testing and Leak Verification
- Emergency Power and Life-Safety Systems Testing
- Deficiency Documentation with Corrective Actions
- Punchlist Resolution Support at Substantial Completion
- Systems O&M Manual Development
- Post-Occupancy Verification and Seasonal Re-Testing (12 months)
- Facilities Team Controls and Maintenance Training
Scope Questions
Pre-Functional Checklist Execution
- Which systems will you require pre-functional checklists for (refer to the commissioning plan or design drawings)?
- How many staged pre-functional walkthroughs per typical occupied zone do you expect before functional testing (for example: terminal device stat, ductwork inspection, control point verification)?
- Who will provide as-built mechanical drawings, updated control point list (CPL), and submittal-responses used to build the pre-functional checklists?
- When do you plan to complete pre-functional checklists relative to the start of functional tests (for example: 2 weeks before, 1 week before, same day)?
- List any site access, safety, or lockout/tagout (LOTO) restrictions that will affect checklist execution (for example: occupied floors, live electrical rooms, constrained rooftop access).
- Confirm whether you require digital checklist forms with photo attachments and timestamped GPS or zone labels tied to each checklist item for traceability.
HVAC Functional Performance Testing
- Select HVAC systems that must be covered by functional performance tests per the design intent and commissioning plan (examples: AHU, RTU, VAV, heat pump, chilled beams).
- Estimate the number of representative sequences of operation to be tested per major air handling unit (for example: economizer modulation, heating/cooling changeover, frost control).
- Identify who will coordinate scheduling of HVAC functional test windows with the mechanical subcontractor and site superintendent.
- Provide the date or milestone when condenser/chilled-water and hot-water systems will be available for full-load HVAC performance tests.
- Provide target acceptance thresholds for HVAC tests drawn from the design basis (for example: supply temperature tolerance ±2°F, airflow variance ±10% of design cfm).
- Specify any LEED enhanced commissioning or local energy-code HVAC test requirements that expand the scope (for example: additional sequences or commissioning agent witnessing).
Controls Sequence and Point-to-Point Testing
- Choose the control sequences from the sequence of operations that must be validated with point-to-point checks (for example: economizer control, condenser staging, chilled-water reset).
- Report the current count of control points on the control point list (CPL) to size point-to-point testing effort.
- Assign who will provide BAS access credentials, a list of IP addresses, and any remote VPN or commissioning tool access required for point-to-point verification.
- Schedule when point-to-point checkout should occur relative to mechanical functional tests and TAB (for example: after pre-functional checklists and preliminary TAB, before final functional test).
- Select the controls testing deliverables you require: annotated CPL, point-to-point field verification log, sequence test scripts, BAS screenshot captures, and trend data exports.
- Indicate whether trending will be enabled for at least 72 hours prior to sequence testing to capture baseline behavior.
Air and Water Balancing
- Pick balance deliverables required from the TAB contractor: certified TAB report, instrument calibration certificates, and as-left airflow and hydronic reports.
- State how many zones or terminal devices require full certified air balancing versus sample spot checks (provide count or percentage).
- Provide who will grant access to central plant equipment and chiller controls for pump speed and valve authority adjustments during TAB.
- Schedule when the preliminary TAB report will be available for review relative to functional testing (for example: at least 7 days before HVAC FPT).
- Set acceptance tolerances for room airflow and terminal device flows based on design documents (for example: ±10% of design cfm, face velocity limits).
- Flag any TAB scheduling constraints such as seasonal water temperatures, chiller sequencing, or occupied-hours restrictions that will affect balancing.
Envelope Integrity Testing (blower door, thermal imaging)
- Choose which envelope tests are required for your project: blower door for airtightness, thermal imaging of façades, or infrared during pressure differentials.
- Indicate how many façades or representative units must be tested to satisfy energy code, LEED, or owner's requirements.
- Name who will provide exterior access (scaffolding, lifts) and safe work plans for thermal imaging and blower door setup.
- State the envelope testing window relative to exterior finishing and glazing installation (for example: after glazing and sealants, before final cladding).
- Provide the required leakage threshold used for acceptance (for example: target ACH50 or maximum cfm/ft2).
- Confirm whether you require thermographic reports with annotated images and location tags for every identified thermal anomaly.
Electrical Systems Functional Testing
- Select electrical systems to include in functional testing: main distribution, panelboards, lighting control, automatic transfer switches (ATS), generator, and UPS integration.
- Specify how many ATS or generator full-load tests are required by specification (for example: one full-load run, two-run schedule).
- Assign who will coordinate utility shutdowns, temporary power, and notification to tenants or critical operations for electrical testing.
- Deliver the date that single-line diagrams (SLD) and as-built electrical drawings will be available for test planning.
- Set acceptance criteria for voltage, frequency, and protective device operation during load testing (for example: ±5% voltage under rated load, transfer within specified ms).
- List any sensitive equipment or systems that require staged outages, vendor witness, or special limitations during electrical testing (for example: data center racks, medical imaging).
Plumbing Functional Testing and Leak Verification
- Select plumbing subsystems requiring functional testing: domestic hot water, chilled/hydronic piping, sanitary risers, storm drains, and specialty systems.
- State the number of fixture groups or risers that must be pressure-tested and inspected for leaks.
- Provide who will perform flushing, sterilization, or bacteriological testing if required for domestic water systems prior to commissioning.
- Schedule when hydrostatic or pneumatic tests should be executed relative to drywall, finishes, and ceiling closures.
- Set acceptance thresholds for flow rates and pressure drops on critical mains and fixture groups (for example: ±10% of design flow).
- Confirm whether you require CCTV sewer line inspection reports and video logs for sanitary/storm piping verification.
Emergency Power and Life-Safety Systems Testing
- Choose life-safety systems that must be tested: emergency lighting, fire alarm interlocks with HVAC, sprinkler flow switches, stair pressurization, and smoke control.
- Specify required generator run conditions: number of full-load runs, duration per run, and required recovery time.
- Provide the authority having jurisdiction (AHJ) or fire marshal contact who must witness or approve life-safety system tests.
- Schedule when fire alarm integration checks should be performed relative to panel energization and fire alarm vendor commissioning.
- Set required acceptance actions and retest protocol if a life-safety interface fails during testing (for example: immediate stop, corrective action timeline).
- List any third-party witnesses, vendor representatives, or AHJ presence required for specific life-safety or emergency power tests.
Deficiency Documentation with Corrective Actions
- What format do you require for deficiency reports and corrective actions: annotated functional test logs, photo evidence, contractor corrective action plans, or shared ticket entries?
- Assign who will own tracking and closure of deficiency items in the shared ticketing channel and provide role titles (for example: facilities lead, commissioning agent, GC superintendent).
- Provide the prioritization criteria to be applied to deficiencies (for example: safety/critical, impacts acceptance, cosmetic) used to sequence corrective work.
- Schedule when re-testing should occur after corrective action completion and what minimum evidence must be submitted for re-test acceptance (for example: data logs, photos, retest report).
- What acceptance criteria will confirm a documented deficiency is resolved (for example: re-test metrics within design tolerance, contractor-signed completion certificate, or owner verification)?
- Outline escalation steps and timelines if a deficiency cannot be resolved before substantial completion (for example: conditional acceptance, warranty holdback, extended testing window).
Punchlist Resolution Support at Substantial Completion
- Choose the punchlist workflow you prefer: live shared ticketing with status updates, periodic consolidated punchlist reports, or daily field updates with photographic evidence.
- List how many named contacts from your facilities and project teams will be authorized to approve punchlist closures (provide names or role counts).
- Assign who will coordinate contractor mobilization and access for punchlist corrections during the substantial completion window.
- Provide the scheduled date for the final punchlist turnover meeting relative to the certificate of occupancy milestone.
- What evidence will validate punchlist closure for owner acceptance (for example: signed-off functional test reports, corrected TAB values, or photographic verification)?
- State any fixed-fee boundaries or explicit out-of-scope items for punchlist support (for example: major system retrofits, tenant-provided equipment, or warranty implementation tasks).
-
Mutual Commit
Finalize commercial and contractual terms, acceptance criteria, dependencies, and the governance needed to execute testing without delaying handover.
Agreement Modules
- Master Services Agreement (MSA)
- Statement of Work (SOW)
- Fee Schedule & Payment Terms
- Acceptance Criteria & Test Governance Agreement
- Site Access & Coordination Addendum
- Change Order Agreement
- Insurance & Indemnity Certificate
- Post-Occupancy Verification Addendum
- Acceptance Sign-Off & Handover Checklist
- Data Processing & Confidentiality Addendum (conditional)
-
Deployment
Coordinate site readiness, execute field testing without delaying completion, and capture test records for transparent deficiency resolution.
-
Site Coordination & Readiness
Confirm access windows, construction sequencing, equipment availability, witness requirements, and named points of contact before fieldwork begins.
Pre-Deployment Questions
Environment and site access
- Which building systems will the seller need physical field access to at the start of deployment? (select all that apply — this tells us which trades and areas to coordinate)
- Is this deployment for a single site or multiple sites? (If multiple, we'll request site‑level readiness for each.)
- Primary site for initial fieldwork (site name and primary area/entrance/floor) — so we know where to stage crews and equipment.
Equipment and materials
- Are all long‑lead or test‑critical equipment items required for initial functional tests delivered and staged on site?
- If any critical equipment is outstanding, list the system, item, and expected arrival week (or write 'none') — this lets us sequence tests without delays.
- Are spare parts, temporary meters, and required access tools provided by the buyer on site or will the seller bring them?
People and ownership
- Provide the named points of contact for field coordination (name, role, best contact method, regular hours) — these people will receive schedule invitations and run sheets.
- Which on‑site roles must be present to witness tests or provide trade support? (select all that apply)
- Are there pre‑qualification or credentialing requirements for seller personnel (safety orientation, badging, background check, insurance certificates)? If yes, indicate which and who issues approval.
Timing and constraints
- Confirm regular site working hours and earliest/latest permissible start times for fieldwork (e.g., M–F 7:00–17:00). If different by area, note differences — so we can schedule visits within allowed windows.
- List any blackout dates or restricted windows (tenant move‑in, public events, major inspections) when fieldwork cannot occur.
- What is the critical acceptance milestone date the deployment must not delay (certificate of occupancy, tenant move‑in, or owner's final acceptance)? If unknown, write 'TBD' — we will treat this as the hard constraint for scheduling.
-
Onsite Testing & Commissioning
Execute pre-functional checks, air/water balancing, functional performance tests, and envelope diagnostics with clear owners and a scheduled test plan.
-
Test Witness & Meeting Records
Document witness sessions, meeting minutes, photographic evidence, and defect dispositions to ensure transparent corrective-action tracking.
Meeting Notes
- Witness Planning and Evidence Protocol
- Onsite Witness Session Template
- Defect Triage and Disposition
- Meeting Records Finalization and Handover Package
- Schedule re-test or follow-up witness session for any tests placed on hold
- Approved evidence checklist and photo/data naming convention to be used on every session.
- Agreed storage location and access/retention rules for witness records on the platform.
- Publish the finalized witness schedule to the shared workspace
- Upload the evidence checklist and photo/data naming convention to the project folder
- Confirm and publish the access list and retention policy for stored records
- Pre-session readiness check
- A completed witness session record that includes minutes, photo log, and raw test data saved to the project folder.
- Any immediate defects or tests on hold recorded with provisional severity and clear next steps.
- Confirmation that all evidence follows the agreed naming convention and metadata requirements.
- Attach the witness session minutes, photo log, and raw test data to the session record in the platform
- Flag any immediate defects in the shared defect tracker with provisional severity and a short description
- Review compiled meeting minutes and witness records
- Final evidence package approved and ready to be linked to the project handover deliverables.
- Any missing evidence items identified with deadlines for completion or replacement.
- Recurring follow-up cadence and escalation path set for unresolved defects.
- Upload the approved evidence package to the platform and link it to the project handover folder
- Publish the finalized meeting minutes and a summary of open items to the shared workspace
- Set recurring check-ins and escalation steps for unresolved items until closed
- Reconcile defects from recent witness records
- Each defect has a recorded disposition and a clear corrective action or required evidence request.
- Remediation target dates and re-witness windows are recorded for all remediate dispositions.
- Items needing more data have a documented evidence list and a deadline for submission.
- Publish the defect disposition log with assigned remediation actions and target dates
- Open high severity defect tickets in the shared tracking channel and link evidence
- List required evidence items for defects needing more data and request them within the agreed deadline
- Confirm scope and success criteria
- Finalized witness schedule with sequenced test windows and time buffers for re-runs.
- Verify photo and data completeness against the checklist
- Agree witness schedule and sequencing
- Examine photographic and measurement evidence per defect
- Run and observe the functional test
- Decide disposition and remediation plan
- Approve final evidence package and access rules
- Capture photographic and data evidence
- Define evidence standard and naming convention
- Document immediate defects and provisional holds
- Confirm sign-off, storage, and access process
- Set remediation timeline and re-witness windows
- Confirm follow-up cadence for unresolved items
-
-
Post-Occupancy Validation & Success
Conduct seasonal verification, confirm deficiency resolution, and maintain a shared ticketing channel for warranty issues and continuous improvement.
Success Reviews
- Post-Occupancy Health Check (weeks 1-4)
- First Performance Measurement (weeks 4-10)
- Acceptance Gate Review (around day 90)
- 6-Month Seasonal Verification Check
- Quarterly Operational Review (ongoing)
Issues & Enhancements
- Log any seasonal remediation tasks with retest windows in the shared ticketing channel.
- Publish the acceptance decision record and attach supporting test evidence.
- Create remediation tasks for all failed or conditional criteria with target retest dates.
- Schedule the verification retest window and reserve required access and equipment.
- Present seasonal test outcomes
- Confirm seasonal verification completion rate is tracking to Commissioning Scope expectations.
- Identify and document any energy performance variances that require remediation.
- Ensure warranty tickets are being resolved and recurring issues are captured for systemic fixes.
- Reconfirm acceptance criteria and owners
- Produce a short summary of energy variance analysis and recommended adjustments.
- Plan any additional envelope or HVAC diagnostics required for the next seasonal window.
- Ticketing channel burn-down review
- Keep warranty ticket backlog reducing in line with burn-down targets from Commissioning Scope.
- Ensure comfort complaint rate is stable or improving and capture root causes for any increases.
- Maintain a prioritized continuous improvement backlog for the next quarter.
- Close or escalate tickets that are aged beyond the agreed SLA and document next steps.
- Schedule any agreed short operational tasks with dates and required site access.
- Update the continuous improvement backlog and circulate priorities for the next quarter.
- Confirm pre-functional checklist completion rate and identify any critical items requiring immediate action.
- Ensure the shared warranty/ticketing channel is operational and contains the initial defect list.
- Agree remediation actions with clear timelines to avoid acceptance delays.
- Publish the initial defect list and pre-functional checklist summary to the shared workspace.
- Enable and verify access for buyer and seller teams to the warranty/ticketing channel.
- Create remediation tasks for all critical open deficiencies with target close dates.
- Present functional test results
- Determine whether percent of functional tests passed is moving toward Commissioning Scope targets.
- Agree remediation and retest timelines to improve median days to close deficiencies to target levels.
- Capture any sequencing or access blockers and document mitigation steps.
- Publish a prioritized retest schedule and required site access windows.
- Log root-cause remediation tasks in the shared ticketing channel with resolution dates.
- Update the functional test tracking spreadsheet with latest pass/fail status.
- Restate numeric acceptance criteria
- Produce a documented acceptance decision tied to the numeric targets in Commissioning Scope.
- List any failed or conditional criteria with a clear remediation and retest timeline.
- Confirm next verification steps and the evidence required to close conditional items.
- Review energy performance variance
- Comfort complaint and trend analysis
- Present consolidated outcome data
- Deficiency closure velocity
- Validate ticketing and communication channels
- Warranty ticket trends and dispositions
- Document pass/fail per criterion
- Continuous improvement backlog
- Root-cause diagnosis for gaps
- Review pre-functional checklist results
- Short operational actions
- Early operational observations
- Confirm retest and sequencing plan
- Adjust operational setpoints or sequences
- Formal acceptance decision
- Agree immediate remediation actions
- Agree remediation and verification timeline for failed items